| Organization | Upper Columbia Salmon Recovery Board Lead Entity |
| Sponsor | Chelan County Commissioners |
| Status | Completed |
| Schedule | Start Date: 7/29/1999 End Date: 8/8/2001 |
| Category | Category: Restoration |
| Type | Date | Funding Org | Funding Program | Match | Amount |
|---|---|---|---|---|---|
| Requested | Chelan County Commissioners | Match | $3,000.00 | ||
| Requested | Recreation and Conservation Office (RCO) | Salmon State Projects | $43,931.00 | ||
| Allocated | 07/17/2001 | Recreation and Conservation Office (RCO) | Salmon State Projects | $43,931.00 | |
| Spent | 08/08/2001 | Chelan County Commissioners | Match | -$0.00 | |
| Spent | 08/08/2001 | Recreation and Conservation Office (RCO) | Salmon State Projects | -$43,931.00 |
| Grant Project Agreement Totals | Proposed | Requested | Allocated | Spent | Balance |
| $5,730.00 | $46,931.00 | $43,931.00 | $43,931.00 | $0.00 |
| Type | Date | Funding Org | Funding Program | Match | Amount |
|---|
| Other Funding Totals | Requested | Allocated | Spent | Balance | |
| Grand Totals | Proposed | Requested | Allocated | Spent | Balance |
| Chinook-Pop (ESU): | Chinook-Upper Columbia River Spring, Wenatchee River, Endangered |
| Chinook2-Pop (ESU): | Chinook-Upper Columbia River Summer/Fall, Not Warranted |
| County: | Chelan |
| HUC12: | Brender Creek-Mission Creek (170200110604) |
| HUC8: | Wenatchee (17020011) |
| Lead Entity Area: | Upper Columbia River |
| Legislative District: | 12 |
| Salmon Recovery Regions: | Upper Columbia River |
| Sections: | 05 |
| Steelhead-Pop (ESU): | Steelhead-Upper Columbia River, Wenatchee River, Threatened |
| Township: | T23NR19E |
| Upper Columbia Assesment Unit: | Mission Creek-Brender Creek |
| Watershed Administrative Unit: | Lower Mission Creek |
| WRIA: | Wenatchee |
| APPLICATION | FINAL | ||||
| RESTORATION METRICS | |||||
Miles of Stream and/or Shoreline Treated or Protected (C.0.b) | 0.50 | mi | 0.50 | mi | |
| Estuarine / Nearshore Project | |||||
*Total Amount Of Estuarine / Nearshore Acres Treated (C.9.b) | 5.00 | acres | 5.00 | acres | |
| Creation of new estuarine area (C.9.q.1) | |||||
Acres of Estuary Created (C.9.q.2) | 1.00 | acres | 1.00 | acres | |
| Estuarine plant removal / control (C.9.j.1) | |||||
Acres of Estuary Treated for plant removal/control (C.9.j.3) | 5.00 | acres | 5.00 | acres | |
| Fish Passage Improvement | |||||
*Miles Of Stream Made Accessible (SRFB) (C.2.b.1) | 1.50 | mi | |||
*Number of blockages / impediments / barriers impeding passage (C.2.b.4) | 1.00 | ||||
Square Miles Of streambed made accessible (C.2.b.2) | |||||
| Fish passage blockages removed or altered (C.2.c.1) | |||||
Change in water flow (fish passage project)(cu feet) | |||||
Number of Blockages/Impediments/Barriers Removed/Altered (C.2.c.2) | |||||
| Instream Habitat Project | |||||
Total Miles Of Instream Habitat Treated (C.4.b) | 0.50 | mi | 0.50 | mi | |
| Channel reconfiguration and connectivity (C.4.c.1) | |||||
Acres Of Channel/Off-Channel Connected Or Added (C.4.c.5) | 1.00 | acres | |||
Instream Pools Created/Added (C.4.c.6) | |||||
Miles of Off-Channel Stream Created or Connected (C.4.c.4) | |||||
Miles of Stream Treated for channel reconfiguration and connectivity (C.4.c.3) | 0.50 | mi | |||
| Channel structure placement (C.4.d.1) | |||||
Acres Of Streambed Treated for channel structure placement (C.4.d.4) | |||||
Miles of Stream Treated for channel structure placement (C.4.d.3) | |||||
Number of structures placed in channel (C.4.d.7) | |||||
Pools Created through channel structure placement (C.4.d.5) | |||||
Yards Of Average Stream-Width At Mid-Point Of Worksite (C.4.d.6) | |||||
| Spawning gravel placement (C.4.f.1) | |||||
Cubic Yards of spawning gravel placed (C.4.f.3) | |||||
Miles of Stream Treated with spawning gravel placement (C.4.f.2) | |||||
| Streambank stabilization (C.4.e.1) | |||||
Miles of Streambank Stabilized (C.4.e.3) | 0.00 | mi | 0.50 | mi | |