CCNRD Irwin Riparian Restoration RM 24.3
#SRP-07-1688 #SRP-07-1688
 Wenatchee Sub-basin Lower Wenatchee CCNRD Irwin Riparian Restoration RM 24.3
Organization Upper Columbia Salmon Recovery Board Lead Entity
Sponsor Chelan County Natural Resources Department
Status Completed
Schedule Start Date: 11/1/2007 End Date: 9/1/2008
Priority 1
Category Category: Restoration
Project Photo
DESCRIPTION
The UPA Wenatchee Riparian Project is located in the Wenatchee River subbasin, a tributary to the Columbia River and was implemented in April 2008. The planting project enhanced 1.64 acres or 1,400 linear feet of riparian habitat directly adjacent to summer Chinook spawning habitat. The UPA Wenatchee Riparian project is part of a regional commitment by the Chelan County Natural Resource Department (CCNRD) to initiate long term habitat and restoration efforts within the Wenatchee River subbasin for Endangered Species Act (ESA) listed species, incorporating the recommendations from the Wenatchee Watershed Planning Unit (WWPU) and Regional Salmon Recovery efforts. The project consisted of the installation of native riparian plants, weed barrier mats, herbivory protection and an irrigation system
Show more  ↓
FUNDING
Proposed Cost $99,932
Requested Funds $0
Allocated Funds $0
Spent Funds $0
Balance $0
FUNDING SOURCES
PROJECT CONTACT
COORDINATOR
LAND OWNER
PARTNER
SPONSOR
PHOTOS

 
LOCATION
Sections:12
Legislative District:12
County:Chelan
Chinook-Pop (ESU):Chinook-Upper Columbia River Spring, Wenatchee River, Endangered
Chinook2-Pop (ESU):Chinook-Upper Columbia River Summer/Fall, Not Warranted
HUC12:Derby Canyon-Wenatchee River (170200110706)
Steelhead-Pop (ESU):Steelhead-Upper Columbia River, Wenatchee River, Threatened
Township:T24NR17E
Lead Entity Area:Upper Columbia
Salmon Recovery Regions:Upper Columbia River
WRIA:Wenatchee
HUC8:Wenatchee (17020011)
View project on a larger map
ACTIVITY-RIPARIAN HABITAT PROJECT PCSRF
* Total Riparian Acres Treated 01.64 Acres
* Total Riparian Miles Streambank Treated 00.27 Miles
Acres Planted in riparian 01.64 Acres
PROJECT SCHEDULE
2008 Construction