MSRF Sletten and Green Habitat Complexity Projects
#SRP-09-13335 #SRP-09-13335
 Methow Sub-basin Upper Methow-Winthrop to Lost River MSRF Sletten and Green Habitat Complexity Projects
Organization Upper Columbia Salmon Recovery Board Lead Entity
Sponsor Methow Salmon Recovery Foundation
Status Completed
Schedule Start Date: 5/31/2009 End Date: 10/30/2009
Category Category: Restoration
Project Photo
DESCRIPTION
This project has been developed by Methow Salmon Recovery Foundation in consultation with WDFW field Engineer Gina McCoy to address continuing shoreline erosion and avulsion that impact these residential properties in the mainstem of the Methow River in the Big Valley reach. The project goal is to increase bank complexity by constructing buried rock and wood structures. These structures are designed to interact with the active channel increasing localized scour, improving pool development during high flow while limiting shoreline erosion. The new strucutres will enhance the function of similar structures placed in mid 90's and 2007.

Green:
The project features include the following design elements:
Install conifer root wads (approximately 24" dia) in excavated trenches landward of the OHWM. Backfill excavated trenches with angular rip-rap (24" minus) to ballast the root wads. Revegetate areas disturbed by construction

The affected area has been previously impacted by flood erosion events. Past bank stabilization work was completed in 2006-7. Prior to that the site lost 100 feet of bank width. The existing structures are not associated with active channel formation at present. The new installation will be intermingled at a steeper angle to improve function.
The project will require excavation of trenches approximately 4-5 feet in width and 4-5 feet in depth for placement of root wads and ballast. Excavation will be timed for late summer low flows to reduce potential impacts to construction from river seepage into excavated trenches. Extensive riparian vegetation will be planted on disturbed areas.

Sletten:
The Project site contains two constructed LWD barb structures and one rock barb bank stabilization structure placed in the mid-1990s by USFWS. The lower LWD structure has partially failed, resulting in bank failure and loss of riparian vegetation. The upper rock barb structure has deformed with several large rocks having dislodged over time. Despite a relatively healthy riparian forest on the floodplain, the landowner was concerned about the exposed bank areas.

Resource agencies (WDFW, Okanogan County) suggested Methow Salmon Recovery Foundation work with the landowner to continue use of more natural alternative to riprap. The resulting project has been developed by MSRF in consultation with WDFW field Engineer Gina McCoy to repair and augment the two large wood structures with additional LWD and reposition 4-5 medium to large rocks within the original footprint of the one rock barb structure. The project should increase bank complexity while reducing bank erosion. MSRF will assit in restoration of riparian vegetation in the area.

The project features include the following design elements:
Add conifer root wads (24" dia) to two existing LWD and rock structures,
Add 24" minus riprap, with a significant percentage of smaller material, landward of the OHWM and buried in two approximately 30' long trenches. Revegetate riparian areas disturbed by construction with native vegetation.


Show more  ↓
FUNDING SOURCES
Bonneville Power Administration (BPA) ($0)Confederated Tribes and Bands of the Yakama Nation (YN) ($0)$0$0
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Allocated05/31/2009Bonneville Power Administration (BPA)$0.00
Allocated05/31/2009Confederated Tribes and Bands of the Yakama Nation (YN)$0.00
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$30,000.00 $0.00 $0.00 $0.00 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
SECONDARY SPONSOR
PHOTOS

Green: pre project view downstream

 
LOCATION
Chinook-Pop (ESU):Chinook-Upper Columbia River Spring, Methow River, Endangered
Chinook2-Pop (ESU):Chinook-Upper Columbia River Summer/Fall, Not Warranted
County:Okanogan
HUC12:Fawn Creek-Methow River (170200080602)
HUC8:Methow (17020008)
Lead Entity Area:Upper Columbia
Legislative District:07
Salmon Recovery Regions:Upper Columbia River
Sections:30
Steelhead-Pop (ESU):Steelhead-Upper Columbia River, Methow River, Threatened
Township:T35NR21E
Upper Columbia Assesment Unit:Methow River-Fawn Creek
Watershed Administrative Unit:Wolf Creek
WRIA:Methow
View project on a larger map