Organization | Upper Columbia Salmon Recovery Board Lead Entity |
Sponsor | City of Okanogan |
Status | Completed |
Schedule | Start Date: 7/29/1999 End Date: 8/20/2001 |
Category | Category: Restoration |
Type | Date | Funding Org | Funding Program | Match | Amount |
---|---|---|---|---|---|
Requested | 07/14/1999 | City of Okanogan | Match | $11,500.00 | |
Requested | 07/14/1999 | Recreation and Conservation Office (RCO) | Salmon State Projects | $40,000.00 | |
Allocated | 08/20/2001 | City of Okanogan | Match | $6,075.03 | |
Allocated | 08/20/2001 | Recreation and Conservation Office (RCO) | Salmon State Projects | $35,856.78 | |
Spent | 01/31/2001 | City of Okanogan | Match | -$6,075.03 | |
Spent | 01/31/2001 | Recreation and Conservation Office (RCO) | Salmon State Projects | -$35,856.78 |
Grant Project Agreement Totals | Proposed | Requested | Allocated | Spent | Balance |
$51,500.00 | $51,500.00 | $41,931.81 | $41,931.81 | $0.00 |
Type | Date | Funding Org | Funding Program | Match | Amount |
---|
Other Funding Totals | Proposed | Requested | Allocated | Spent | Balance |
Grand Totals | Proposed | Requested | Allocated | Spent | Balance |
Chinook-Pop (ESU): | Chinook-Upper Columbia River Spring, Okanogan River, Threatened |
Chinook2-Pop (ESU): | Chinook-Upper Columbia River Summer/Fall, Not Warranted |
City Areas: | Okanogan |
County: | Okanogan |
HUC12: | Green Lake-Salmon Creek (170200062004) |
HUC8: | Okanogan (17020006) |
Lead Entity Area: | Upper Columbia |
Legislative District: | 07 |
Salmon Recovery Regions: | Upper Columbia River |
Sections: | 08 |
Steelhead-Pop (ESU): | Steelhead-Upper Columbia River, Okanogan River, Threatened |
Township: | T33NR26E |
Upper Columbia Assesment Unit: | Salmon Creek-Lower |
Watershed Administrative Unit: | Lower Salmon Creek |
WRIA: | Okanogan |
APPLICATION | FINAL | ||||
RESTORATION METRICS | |||||
Miles of Stream and/or Shoreline Treated or Protected (C.0.b) | 0.06 | mi | 0.06 | mi | |
Fish Passage Improvement | |||||
*Miles Of Stream Made Accessible (SRFB) (C.2.b.1) | 14.00 | mi | 14.00 | mi | |
*Number of blockages / impediments / barriers impeding passage (C.2.b.4) | 3.00 | ||||
Square Miles Of streambed made accessible (C.2.b.2) | |||||
Culvert installed or improved (C.2.f.1) | |||||
Miles of stream made accessible by culvert installation/repair (C.2.f.3) | 0.00 | mi | 0.00 | mi | |
Number of culverts (C.2.f.2) | |||||
Fish passage blockages removed or altered (C.2.c.1) | |||||
Number of Blockages/Impediments/Barriers Removed/Altered (C.2.c.2) | 3.00 | 3.00 | |||
Road-crossing removal (C.2.i.1) | |||||
Miles of stream made accessible by road crossing removal (C.2.i.3) | 14.00 | mi | 14.00 | mi | |
Number of road-crossings (C.2.i.2) | |||||
Instream Habitat Project | |||||
Total Miles Of Instream Habitat Treated (C.4.b) | |||||
Channel structure placement (C.4.d.1) | |||||
Acres Of Streambed Treated for channel structure placement (C.4.d.4) | |||||
Miles of Stream Treated for channel structure placement (C.4.d.3) | |||||
Number of structures placed in channel (C.4.d.7) | |||||
Pools Created through channel structure placement (C.4.d.5) | |||||
Yards Of Average Stream-Width At Mid-Point Of Worksite (C.4.d.6) |