Dryden Fish Enhancement CMZ Project
#04-1461 #04-1461
 Wenatchee Sub-basin Lower Wenatchee Dryden Fish Enhancement CMZ Project
Organization Upper Columbia Salmon Recovery Board Lead Entity
Sponsor Chelan County Public Utilities District
Status Completed
Schedule Start Date: 1/1/2005 End Date: 7/8/2008
Priority 1
Category Category: Restoration
Project Photo
DESCRIPTION
The Dryden project is a cooperative habitat enhancement project designed to help endangered spring chinook, endangered summer steelhead trout and other salmonids within the lower Wentachee River. The project site is owned by WDFW and consists of 8.8 acres of floodplain and riparian shoreline located adjacent to the Wenatchee River. The site was mined as part of a gravel pit operation in the l950's. A dike isolates the property from the river along 1500 feet of riverfront. The project will breach a portion of the dike and construct an inlet structure and a series of inland channels. The inlet itself will be an open channel design and will be armored with native oversized round rock. Large rock, logs, and rootwads will be placed as habitat structures in the channels. Vegetation will be planted on the channel banks and all areas disturbed through construction. Development along the main stem Wenatchee River has caused significant loss of off-channel habitat and floodplain function. Much off-channel habitat has been taken out of salmonid production through past land use practices and stream habitat alterations and fragmentation. The objective of this project is to create prime, high quality, rear-round habitat, predator escape cover, and high flow refuge areas for salmonids.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested07/13/2004Chelan County PUDMatch$34,000.00
Requested07/13/2004Salmon Recovery Funding BoardSalmon State Projects$146,000.00
Allocated07/08/2008Chelan County PUDMatch$34,000.04
Allocated07/08/2008Salmon Recovery Funding BoardSalmon Federal Projects$145,750.35
Spent07/08/2008Chelan County PUDMatch-$34,000.04
Spent07/08/2008Salmon Recovery Funding BoardSalmon Federal Projects-$145,750.35
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$179,750.39 $180,000.00 $179,750.39 $179,750.39 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PROJECT CONTACT
GRANT MANAGER
PARTNER
SPONSOR
PHOTOS

 
LOCATION
Legislative District 2022:12
Sections:26
County:Chelan
Chinook-Pop (ESU):Chinook-Upper Columbia River Spring, Wenatchee River, Endangered
Chinook2-Pop (ESU):Chinook-Upper Columbia River Summer/Fall, Not Warranted
HUC12:Ollala Canyon-Wenatchee River (170200110707)
Steelhead-Pop (ESU):Steelhead-Upper Columbia River, Wenatchee River, Threatened
Township:T24NR18E
Lead Entity Area:Upper Columbia
Salmon Recovery Regions:Upper Columbia River
WRIA:Wenatchee
HUC8:Wenatchee (17020011)
View project on a larger map
ACTIVITY-FISH PASSAGE IMPROVEMENT PCSRF
* Miles of Stream Made Accessible 00.2 Miles
*Number of Blockages/Impediments/Barriers Impeding Passage 01 Number
ACTIVITY-INSTREAM HABITAT PROJECT PCSRF
Miles of Streambank Stabilized
100%
0.02 Actual
0.02 Planned
Miles
Total Miles Of Instream Habitat Treated
100%
0.14 Actual
0.14 Planned
Miles
Acres Of Off-Channel/Floodplain Connected Or Added 00.2 Acres
Miles of Off-Channel Stream Created 00.2 Miles
Number of structures placed in channel 03 Number
ACTIVITY-RIPARIAN HABITAT PROJECT PCSRF
* Total Riparian Acres Treated 01 Acres
* Total Riparian Miles Streambank Treated 00.2 Miles
Acres of riparian treated for plant removal/control 00.2 Acres
Acres Planted in riparian 00.2 Acres
ADDITIONAL INFORMATION