WSDOT Mill Creek Culvert Replacement
#SRP-05-10645 #SRP-05-10645
 Wenatchee Sub-basin Nason Creek WSDOT Mill Creek Culvert Replacement
Organization Upper Columbia Salmon Recovery Board Lead Entity
Sponsor Department of Transportation (WSDOT)
Status Completed
Schedule Start Date: 1/1/2005 End Date: 9/1/2006
Category Category: Restoration
Project Photo
DESCRIPTION
This is WDFW site 990282. WADOT replaced a culvert under highway 2 in 2006. The 2006 project replaced the undersized culvert with a a 0.49 m outfall drop to a bottomless structural plate arch with natural streambed material placed throughout the culvert. The new crossing restores access to over 11,500 m (>7 miles) of habitat to resident O. mykiss, cutthroat, and bull trout, and perhaps ~ 0.5 miles of potential steelhead habitat.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
LANDOWNER
PHOTOS

Mill Creek After Culvert Replacement

 
LOCATION
Chinook-Pop (ESU):Chinook-Upper Columbia River Spring, Wenatchee River, Endangered
Chinook2-Pop (ESU):Chinook-Upper Columbia River Summer/Fall, Not Warranted
County:Chelan
HUC12:Upper Nason Creek (170200110201)
HUC8:Wenatchee (17020011)
Lead Entity Area:Upper Columbia
Legislative District:12
Salmon Recovery Regions:Upper Columbia River
Sections:05
Steelhead-Pop (ESU):Steelhead-Upper Columbia River, Wenatchee River, Threatened
Township:T26NR15E
Upper Columbia Assesment Unit:Upper Nason Creek
Watershed Administrative Unit:Upper Nason
WRIA:Wenatchee
View project on a larger map
ADDITIONAL INFORMATION