Organization | Skagit Watershed Council Lead Entity |
Sponsor | Skagit County |
Status | Completed |
Schedule | Start Date: 7/29/1999 End Date: 9/14/2000 |
Category | Category: Restoration |
Type | Date | Funding Org | Funding Program | Match | Amount |
---|---|---|---|---|---|
Requested | Recreation and Conservation Office (RCO) | Salmon State Projects | $47,500.00 | ||
Requested | Skagit County | Match | $371,000.00 | ||
Allocated | 09/14/2000 | Recreation and Conservation Office (RCO) | Salmon State Projects | $47,500.00 | |
Allocated | 09/14/2000 | Skagit County | Match | $413,243.98 | |
Spent | 09/06/2000 | Recreation and Conservation Office (RCO) | Salmon State Projects | -$47,500.00 | |
Spent | 09/06/2000 | Skagit County | Match | -$413,243.98 |
Grant Project Agreement Totals | Proposed | Requested | Allocated | Spent | Balance |
$460,743.98 | $418,500.00 | $460,743.98 | $460,743.98 | $0.00 |
Type | Date | Funding Org | Funding Program | Match | Amount |
---|
Other Funding Totals | Proposed | Requested | Allocated | Spent | Balance |
Grand Totals | Proposed | Requested | Allocated | Spent | Balance |
Chinook-Pop (ESU): | Chinook-Puget Sound, Lower Skagit River, Threatened |
Chum-Pop (ESU): | Chum-Puget Sound/Strait of Georgia, Not Warranted |
Coho-Pop (ESU): | Coho-Puget Sound/Strait of Georgia, Species of Concern |
County: | Skagit |
HUC12: | Aldon Creek-Skagit River (171100051104) |
HUC8: | Upper Skagit (17110005) |
Lead Entity Area: | Skagit Watershed Council |
Legislative District: | 39 |
Pink-Pop (ESU): | Pink-Odd Year, Not Warranted |
Puget Sound Action Areas: | Whidbey Island |
Salmon Recovery Regions: | Puget Sound |
Sections: | 33 |
Skagit Tiers: | Tier 3 Sediment or Hydrology Impaired |
Steelhead-Pop (ESU): | Steelhead-Puget Sound, Skagit River, Threatened |
Township: | T35NR09E |
Watershed Administrative Unit: | Corkindale |
WRIA: | Upper Skagit |
APPLICATION | FINAL | ||||
RESTORATION METRICS | |||||
Miles of Stream and/or Shoreline Treated or Protected (C.0.b) | 0.02 | mi | 0.02 | mi | |
Fish Passage Improvement | |||||
*Miles Of Stream Made Accessible (SRFB) (C.2.b.1) | 1.10 | mi | 1.10 | mi | |
*Number of blockages / impediments / barriers impeding passage (C.2.b.4) | 1.00 | ||||
Square Miles Of streambed made accessible (C.2.b.2) | |||||
Culvert installed or improved (C.2.f.1) | |||||
Miles of stream made accessible by culvert installation/repair (C.2.f.3) | 1.10 | mi | 1.10 | mi | |
Number of culverts (C.2.f.2) | |||||
Fish passage blockages removed or altered (C.2.c.1) | |||||
Change in water flow (fish passage project)(cu feet) | |||||
Number of Blockages/Impediments/Barriers Removed/Altered (C.2.c.2) | 1.00 | 1.00 | |||
Road-crossing removal (C.2.i.1) | |||||
Miles of stream made accessible by road crossing removal (C.2.i.3) | 0.00 | mi | 0.00 | mi | |
Number of road-crossings (C.2.i.2) | |||||
Site Stewardship Project | |||||
Restored land maintained (C.11.c.1) | |||||
Acres of restored land maintained (C.11.c.2) |