Hansen Creek Reach 3 & 4 Restoration
#08-1754 #08-1754
 Skagit River Skagit River Middle Hansen Creek Reach 3 & 4 Restoration
Organization Skagit Watershed Council Lead Entity
Sponsor Upper Skagit Indian Tribe
Status Completed
Schedule Start Date: 12/11/2008 End Date: 5/23/2011
Category Category: Restoration
Project Photo
DESCRIPTION
The project objectives achieved for the Hansen Creek alluvial fan and wetland restoration were restoration of the historic floodplain, riparian habitat and self-sustaining hydrologic and sediment transport processes for improved salmon habitat and productivity. The project restored 140 acres of pasture and isolated depressional wetlands into 53 acres of alluvial fan, 87 acres of riverine forest, and flow-through wetlands. The combination of alluvial fan and forested, flow-through wetland restoration features include wood and grade control in the mainstem, wood in the fan and wetlands and native plantings and/or seeding for the entire site. The project restored floodplain functions that moderate the influences of high-discharge events, improve sediment transport, gravel sorting, water storage, and increase sinuosity and channel complexity in the main stem and promote formation of complex side channels for fish access and use. Flood flows and sediment movement into the floodplain build a water reservoir that contributes to flows in the dry season, restore stream processes that support productive aquatic habitats, and reduce downstream flooding and the upstream headcutting present today. Freshwater spawning and rearing limitations are the result of habitat loss, degradation and fragmentation. This project implements identified strategies in the Skagit Chinook Recovery Plan, chapters 9 and 10 for both spawning and rearing habitat restoration.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested09/08/2008Recreation and Conservation Office (RCO)Salmon State Projects$663,915.00
Requested09/08/2008Upper Skagit Indian TribeMatch$1,993,085.00
Allocated12/11/2008Recreation and Conservation Office (RCO)Salmon State Projects$663,915.00
Allocated12/11/2008Upper Skagit Indian TribeMatch$1,842,915.00
Spent05/23/2011Recreation and Conservation Office (RCO)Salmon State Projects-$663,915.00
Spent05/23/2011Upper Skagit Indian TribeMatch-$1,842,915.00
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$2,506,830.00 $2,657,000.00 $2,506,830.00 $2,506,830.00 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Puget Sound, Lower Skagit River, Threatened
Chum-Pop (ESU):Chum-Puget Sound/Strait of Georgia, Not Warranted
Coho-Pop (ESU):Coho-Puget Sound/Strait of Georgia, Species of Concern
County:Skagit
HUC12:Hansen Creek-Skagit River (171100070107)
HUC8:Lower Skagit (17110007)
Lead Entity Area:Skagit Watershed Council
Legislative District:39
Pink-Pop (ESU):Pink-Odd Year, Not Warranted
Puget Sound Action Areas:Whidbey Island
Salmon Recovery Regions:Puget Sound
Sections:17
Skagit Reaches:Hansen Creek
Skagit Tiers:Tier 3 Sediment or Hydrology Impaired
Steelhead-Pop (ESU):Steelhead-Puget Sound, Skagit River, Threatened
Township:T35NR05E
Watershed Administrative Unit:Hansen Creek
WRIA:Lower Skagit - Samish
View project on a larger map

Related Projects

  APPLICATION FINAL 
RESTORATION METRICS
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
2.47mi0.00mi
Estuarine / Nearshore Project    
*Total Amount Of Estuarine / Nearshore Acres Treated (C.9.b)
0.00acres0.00acres
 Creation of new estuarine area (C.9.q.1)    
Acres of Estuary Created (C.9.q.2)
140.00acres0.00acres
 Estuarine plant removal / control (C.9.j.1)    
Acres of Estuary Treated for plant removal/control (C.9.j.3)
0.00acres0.00acres
Fish Passage Improvement    
*Miles Of Stream Made Accessible (SRFB) (C.2.b.1)
0.00mi
*Number of blockages / impediments / barriers impeding passage (C.2.b.4)
0.00
Square Miles Of streambed made accessible (C.2.b.2)
0.00sq mi
 Fish passage blockages removed or altered (C.2.c.1)    
Change in water flow (fish passage project)(cu feet)
0.00cfs
Number of Blockages/Impediments/Barriers Removed/Altered (C.2.c.2)
0.00
Instream Habitat Project    
Total Miles Of Instream Habitat Treated (C.4.b)
4.94mi0.00mi
 Channel structure placement (C.4.d.1)    
Acres Of Streambed Treated for channel structure placement (C.4.d.4)
25.00acres
Miles of Stream Treated for channel structure placement (C.4.d.3)
0.50mi
Number of structures placed in channel (C.4.d.7)
272.00
Pools Created through channel structure placement (C.4.d.5)
30.00
Yards Of Average Stream-Width At Mid-Point Of Worksite (C.4.d.6)
10.00yd
 Streambank stabilization (C.4.e.1)    
Miles of Streambank Stabilized (C.4.e.3)
2.47mi0.20mi
Riparian Habitat Project    
*Total Riparian Acres Treated (C.5.b.2)
0.00acres140.00acres
*Total Riparian Miles Streambank Treated (C.5.b.1)
4.94mi4.94mi
 Riparian Plant removal / control (C.5.h.1)    
Acres of riparian treated for plant removal/control (C.5.h.3)
40.00acres20.00acres