Turners Bay Road Removal - Construction
#09-1441 #09-1441
 Nearshore Chinook Nearshore Projects Turners Bay Road Removal - Construction
Organization Skagit Watershed Council Lead Entity
Sponsor Skagit River System Cooperative
Status Completed
Schedule Start Date: 12/10/2009 End Date: 9/14/2012
Category Category: Restoration
Project Photo
DESCRIPTION
This project enhanced fish access and restored tidal inundation to a 7.3 acre portion of a 59.4 acre tidal channel lagoon and marsh complex. Formerly, upper portions of the salt marsh received muted tidal volumes and fish access was severely limited due to a road crossing (Similk Bay Road) and a non-functioning tide gate. An extensive feasibility study was completed in 2007 (McBride 2007) that identified removal of this road as the restoration action with the greatest habitat benefit. The study also documented portions of the site that had been ditched and/or filled, and identified creosote-treated debris on the site from a previous log storage operation. The design and permitting of the proposal was completed in SRFB project 07-1808N. Project components included removing a portion of the road, elevation of a County Roadway, realignment of utilities, removal of debris, removal of undersized culverts, and native vegetation restoration. The finished project now allows unimpeded fish access and tidal exchange that will allow for re-establishment native vegetation communities in isolated marsh fragments. These actions also encourage project longevity by addressing impaired processes that maintained the historic lagoon. Restoration of these processes translates to increased habitat area and quality for fry migrant Chinook and other native salmon species, and will benefit forage fish and wildlife species as well. Final designs and permit documents were developed as part a 2007 SRFB grant (07-1808N).
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested10/14/2009Skagit River System CooperativeMatch$128,689.00
Requested10/14/2009Recreation and Conservation Office (RCO)Puget Sound Acq. & Restoration$671,073.00
Allocated12/10/2009Skagit River System CooperativeMatch$128,689.00
Allocated12/10/2009Recreation and Conservation Office (RCO)Puget Sound Acq. & Restoration$671,073.00
Spent09/14/2012Skagit River System CooperativeMatch-$128,689.00
Spent09/14/2012Recreation and Conservation Office (RCO)Puget Sound Acq. & Restoration-$671,073.00
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$799,762.00 $799,762.00 $799,762.00 $799,762.00 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
ALT PROJECT CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Puget Sound, Threatened
Chum-Pop (ESU):Chum-Puget Sound/Strait of Georgia, Not Warranted
Coho-Pop (ESU):Coho-Puget Sound/Strait of Georgia, Species of Concern
County:Skagit
HUC12:Fidalgo Island-Frontal Similk Bay (171100190101)
HUC8:Puget Sound (17110019)
Lead Entity Area:Skagit Watershed Council
Legislative District:10
Pink-Pop (ESU):Pink-Odd Year, Not Warranted
Puget Sound Action Areas:Whidbey Island
Salmon Recovery Regions:Puget Sound
Sections:03
Township:T34NR02E
Watershed Administrative Unit:Fidalgo Island
WRIA:Lower Skagit - Samish
View project on a larger map

Related Projects

  APPLICATION FINAL 
RESTORATION METRICS
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
0.00mi0.00mi
Estuarine / Nearshore Project    
*Total Amount Of Estuarine / Nearshore Acres Treated (C.9.b)
0.00acres59.40acres
 Creation of new estuarine area (C.9.q.1)    
Acres of Estuary Created (C.9.q.2)
59.40acres7.20acres
 Debris removal (C.9.n.1)    
Acres Treated for debris removal (C.9.n.2)
0.50acres
 Estuarine plant removal / control (C.9.j.1)    
Acres of Estuary Treated for plant removal/control (C.9.j.3)
0.00acres0.50acres
 Regrading of slope (C.9.i.1)    
Acres of Estuary Treated through slope regrading (C.9.i.2)
0.10acres
 Shoreline armor removal or modification (C.9.k.1)    
Acres of Shoreline Treated for armor modification/removal (C.9.k.3)
0.20acres
Miles of Shoreline Treated for armor modification/removal (C.9.k.2)
0.09mi
 Tidegate alteration / removal (C.9.e.1)    
Acres opened To Fish Passage through tidegate alteration/removal (C.9.e.3)
7.20acres
Miles of stream made accessible by removal or modification of tidegate
Number of Tidegates Altered/Removed To Allow Fish Passage (C.9.e.2)
1.00
Fish Passage Improvement    
*Miles Of Stream Made Accessible (SRFB) (C.2.b.1)
0.00mi0.50mi
*Number of blockages / impediments / barriers impeding passage (C.2.b.4)
1.00
Square Miles Of streambed made accessible (C.2.b.2)
0.05sq mi
 Culvert installed or improved (C.2.f.1)    
Miles of stream made accessible by culvert installation/repair (C.2.f.3)
0.00mi0.00mi
Number of culverts (C.2.f.2)
0.00
 Fish passage blockages removed or altered (C.2.c.1)    
Number of Blockages/Impediments/Barriers Removed/Altered (C.2.c.2)
2.001.00
 Road-crossing removal (C.2.i.1)    
Miles of stream made accessible by road crossing removal (C.2.i.3)
0.00mi0.50mi
Number of road-crossings (C.2.i.2)
1.00
Site Stewardship Project    
 Restored land maintained (C.11.c.1)    
Acres of restored land maintained (C.11.c.2)
0.00acres
Upland Habitat And Sediment Project    
Acres of Upland Habitat Area Treated (C.6.b.1)
0.00acres
Miles of Road Treated (C.6.b.2)
0.00mi
 Road drainage system improvements and reconstruction (C.6.c.1)    
Average width of road treated for drainage improvements and reconstruction (C.6.c.3)
Miles of Road Treated for drainage improvements and reconstruction (C.6.c.2)
0.10mi