Finney Roads Erosion Control
#06-2213 #06-2213
Organization Skagit Watershed Council Lead Entity
Sponsor Skagit Conservation District
Status Completed
Schedule Start Date: 4/30/2007 End Date: 7/14/2009
Category Category: Restoration
Project Photo
DESCRIPTION
Skagit Conservation District is partnered with USFS on erosion reduction project to reduce the risk of road failures, erosion and their negative effects on Finney Creek and Skagit River. Finney Creek, once a WDFW index stream for Chinook, has 11.5 miles of anadromous fish habitat and 11 miles of resident fish habitat. Sediment from Finney Creek has negatively affected the water quality of Skagit River since the mid-1980's downstream of RM 47.5. Finney Creek is listed as an impaired water body for elevated temperature. This project consisted of culvert replacement, fill stabilization and road decommissioning. This roadwork was identified in 1992 during a road deficiency survey and again in 1995 following storm activity. Road prioritization is based on risk ratings and inventoried drainage deficiencies. This project is the last in a series of projects, using conventional road treatment methods that address 10.8 miles of high-risk FS roads, for the upper 60 % of the watershed. Results: Water quality will improve and the risk of landslides/sediment delivery will incrementally be reduced. This action is expected to contribute to the incremental reduction of road- associated failures and other sedimentation that would occur from water collection and concentration. This project targets the limiting factor of egg to fry survival due to sedimentation for native Chinook, Coho, steelhead and Dolly Varden.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested08/23/2006Skagit Conservation DistrictMatch$45,000.00
Requested08/23/2006Recreation and Conservation Office (RCO)Salmon State Projects$253,810.00
Allocated07/14/2009Skagit Conservation DistrictMatch$50,883.54
Allocated07/14/2009Recreation and Conservation Office (RCO)Salmon Federal Projects$273,996.58
Spent07/14/2009Skagit Conservation DistrictMatch-$50,883.54
Spent07/14/2009Recreation and Conservation Office (RCO)Salmon Federal Projects-$273,996.58
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$324,881.00 $298,810.00 $324,880.12 $324,880.12 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
ALT PROJECT CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Puget Sound, Lower Skagit River, Outside anadromous area
Chum-Pop (ESU):Chum-Puget Sound/Strait of Georgia, Not Warranted
Coho-Pop (ESU):Coho-Puget Sound/Strait of Georgia, Species of Concern
County:Skagit
HUC12:Upper Finney Creek (171100070101)
HUC8:Lower Skagit (17110007)
Lead Entity Area:Skagit Watershed Council
Legislative District:39
Pink-Pop (ESU):Pink-Odd Year, Not Warranted
Puget Sound Action Areas:Whidbey Island
Salmon Recovery Regions:Puget Sound
Sections:26
Sections:35
Skagit Tiers:Tier 3 Sediment or Hydrology Impaired
Steelhead-Pop (ESU):Steelhead-Puget Sound, Skagit River, Outside anadromous area
Township:T34NR08E
Watershed Administrative Unit:Finney
WRIA:Upper Skagit
View project on a larger map
  APPLICATION FINAL 
RESTORATION METRICS
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
0.10mi0.10mi
Upland Habitat And Sediment Project    
Acres of Upland Habitat Area Treated (C.6.b.1)
10.00acres10.00acres
Miles of Road Treated (C.6.b.2)
10.80mi11.08mi
 Erosion control structures (C.6.e.1)    
Acres Treated for erosion control (C.6.e.2)
0.00acres
Number of Erosion/Sediment Control Installations (C.6.e.3)
188.00
 Road abandonment (C.6.d.1)    
Average width of road abandoned (in whole yards) (C.6.d.3)
0.00yd
Miles of Road Abandoned (C.6.d.2)
0.00mi
 Road drainage system improvements and reconstruction (C.6.c.1)    
Average width of road treated for drainage improvements and reconstruction (C.6.c.3)
0.00yd
Miles of Road Treated for drainage improvements and reconstruction (C.6.c.2)
0.00mi
ADDITIONAL INFORMATION