Organization | Stillaguamish River Salmon Recovery Co-Lead Entity |
Sponsor | Stillaguamish Flood Control District |
Status | Completed |
Schedule | Start Date: 3/17/2000 End Date: 7/6/2005 |
Category | Category: Restoration |
Type | Date | Funding Org | Funding Program | Match | Amount |
---|---|---|---|---|---|
Requested | 02/05/2000 | Stillaguamish Flood Control District | Match | $217,670.00 | |
Requested | 02/05/2000 | Recreation and Conservation Office (RCO) | Salmon State Projects | $253,520.00 | |
Allocated | 07/06/2005 | Recreation and Conservation Office (RCO) | Salmon State Projects | $185,893.52 | |
Allocated | 07/06/2005 | Stillaguamish Flood Control District | Match | $192,513.66 | |
Spent | 06/21/2005 | Recreation and Conservation Office (RCO) | Salmon State Projects | -$185,893.52 | |
Spent | 06/21/2005 | Stillaguamish Flood Control District | Match | -$192,513.66 |
Grant Project Agreement Totals | Proposed | Requested | Allocated | Spent | Balance |
$375,408.00 | $471,190.00 | $378,407.18 | $378,407.18 | $0.00 |
Type | Date | Funding Org | Funding Program | Match | Amount |
---|
Other Funding Totals | Proposed | Requested | Allocated | Spent | Balance |
Grand Totals | Proposed | Requested | Allocated | Spent | Balance |
Chinook-Pop (ESU): | Chinook-Puget Sound, South Fork Stillaguamish River, Threatened |
Chum-Pop (ESU): | Chum-Puget Sound/Strait of Georgia, Not Warranted |
Coho-Pop (ESU): | Coho-Puget Sound/Strait of Georgia, Species of Concern |
County: | Snohomish |
HUC12: | Stillaguamish River-Frontal Port Susan (171100080304) |
HUC8: | Stillaguamish (17110008) |
Lead Entity Area: | Stillaguamish River |
Legislative District: | 10 |
Pink-Pop (ESU): | Pink-Odd Year, Not Warranted |
Puget Sound Action Areas: | Whidbey Island |
Salmon Recovery Regions: | Puget Sound |
Sections: | 05 |
Steelhead-Pop (ESU): | Steelhead-Puget Sound, Stillaguamish River, Threatened |
Township: | T31NR04E |
Watershed Administrative Unit: | Lower Stillaguamish River |
WRIA: | Stillaguamish |
APPLICATION | FINAL | ||||
RESTORATION METRICS | |||||
Miles of Stream and/or Shoreline Treated or Protected (C.0.b) | 8.50 | mi | 6.90 | mi | |
Estuarine / Nearshore Project | |||||
*Total Amount Of Estuarine / Nearshore Acres Treated (C.9.b) | 5.00 | acres | |||
Tidegate alteration / removal (C.9.e.1) | |||||
Acres opened To Fish Passage through tidegate alteration/removal (C.9.e.3) | 42.00 | acres | |||
Miles of stream made accessible by removal or modification of tidegate | |||||
Number of Tidegates Altered/Removed To Allow Fish Passage (C.9.e.2) | 1.00 | ||||
Instream Habitat Project | |||||
Total Miles Of Instream Habitat Treated (C.4.b) | 0.00 | mi | 7.00 | mi | |
Plant removal/control (C.4.g.1) | |||||
Acres of Streambed Treated for plant removal/control (C.4.g.4) | 34.00 | acres | |||
Miles of Stream Treated for plant removal/control (C.4.g.3) | 7.00 | mi | |||
Streambank stabilization (C.4.e.1) | |||||
Miles of Streambank Stabilized (C.4.e.3) | 0.00 | mi | 0.01 | mi | |
Riparian Habitat Project | |||||
*Total Riparian Acres Treated (C.5.b.2) | 42.00 | acres | |||
*Total Riparian Miles Streambank Treated (C.5.b.1) | 7.00 | mi | |||
Fencing (C.5.d.1) | |||||
Acres of Riparian Area Protected by fencing (C.5.d.3) | 33.00 | acres | |||
Miles of Fence Along Stream (C.5.d.2) | 2.00 | mi | |||
Planting (C.5.c.1) | |||||
Acres Planted in riparian (C.5.c.3) | 33.00 | acres | |||
Riparian exclusion C.5.e.1) | |||||
Acres of Riparian Area That Had Livestock Removed (C.5.e.2) | 15.00 | acres | |||
Miles of Streambank Protected from livestock (other than fencing) (C.5.e.3) | 7.00 | mi |