zis a ba Estuary Restoration
#16-1356 #16-1356
Organization Stillaguamish River Salmon Recovery Co-Lead Entity
Sponsor Stillaguamish Tribe of Indians
Status Completed
Schedule Start Date: 8/11/2016 End Date: 10/30/2019
Category Category: Restoration
Project Photo
DESCRIPTION
We propose to restore tidal and riverine influence to approximately 88 acres of land currently protected by dikes. We will build a setback levee to protecting surrounding property owners, and grade the site in such a way as to encourage natural tidal channel development while protecting infrastructure that traverses the property. The project is designed to restore estuary rearing habitat for juvenile salmonids, especially ESA-listed Chinook populations of the Stillaguamish and the Skagit.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested06/28/2016Stillaguamish Tribe of IndiansMatch$605,400.00
Requested06/28/2016Recreation and Conservation Office (RCO)Salmon State Projects$967,500.00
Allocated09/18/2019Recreation and Conservation Office (RCO)General Habitat Fed Project$90,504.00
Allocated09/18/2019Recreation and Conservation Office (RCO)Salmon State Projects$335,254.00
Allocated09/18/2019Stillaguamish Tribe of IndiansMatch$470,000.00
Allocated09/18/2019Recreation and Conservation Office (RCO)Puget Sound Acq. & Restoration$632,246.00
Spent01/08/2018Recreation and Conservation Office (RCO)Puget Sound Acq. & Restoration-$632,246.00
Spent01/08/2019Recreation and Conservation Office (RCO)General Habitat Fed Project-$90,504.00
Spent10/29/2019Recreation and Conservation Office (RCO)Salmon State Projects-$335,254.00
Spent10/29/2019Stillaguamish Tribe of IndiansMatch-$470,000.00
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$1,638,783.00 $1,572,900.00 $1,528,004.00 $1,528,004.00 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Puget Sound, South Fork Stillaguamish River, Threatened
Chum-Pop (ESU):Chum-Puget Sound/Strait of Georgia, Not Warranted
Coho-Pop (ESU):Coho-Puget Sound/Strait of Georgia, Species of Concern
County:Snohomish
HUC12:Stillaguamish River-Frontal Port Susan (171100080304)
HUC8:Stillaguamish (17110008)
Lead Entity Area:Stillaguamish River
Legislative District:10
Pink-Pop (ESU):Pink-Odd Year, Not Warranted
Puget Sound Action Areas:Whidbey Island
Salmon Recovery Regions:Puget Sound
Sections:25
Steelhead-Pop (ESU):Steelhead-Puget Sound, Stillaguamish River, Threatened
Township:T32NR03E
Watershed Administrative Unit:Lower Stillaguamish River
WRIA:Stillaguamish
View project on a larger map

Related Projects

  APPLICATION FINAL 
RESTORATION METRICS
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
1.30mi1.30mi
Estuarine / Nearshore Project    
*Total Amount Of Estuarine / Nearshore Acres Treated (C.9.b)
87.70acres87.70acres
 Channel modification (C.9.c.1)    
Acres of Estuary Treated (C.9.c.3)
4.40acres4.40acres
Yards (linear measure) of Channel Modified/Created (C.9.c.2)
5,700.00yd
 Dike Or berm modification / removal (C.9.d.1)    
Acres of Habitat Made Available To Salmonids through dike or berm modification/removal (C.9.d.3)
87.70acres87.70acres
Miles Of Dikes Modified/Removed (C.9.d.2)
1.30mi1.30mi
 Estuarine planting or native plant establishment (C.9.r.1)    
Acres of Estuarine planting or native plant establishment (C.9.r.3)
2.10acres40.00acres
 Fill placement (C.9.h.1)    
Acres of Estuary Treated with fill placement (C.9.h.2)
6.10acres6.10acres
 Regrading of slope (C.9.i.1)    
Acres of Estuary Treated through slope regrading (C.9.i.2)
10.00acres10.00acres
 Tidegate alteration / removal (C.9.e.1)    
Acres opened To Fish Passage through tidegate alteration/removal (C.9.e.3)
87.70acres87.70acres
Miles of stream made accessible by removal or modification of tidegate
Number of Tidegates Altered/Removed To Allow Fish Passage (C.9.e.2)
1.001.00
Instream Habitat Project    
Total Miles Of Instream Habitat Treated (C.4.b)
1.30mi
 Channel structure placement (C.4.d.1)    
Miles of Stream Treated for channel structure placement (C.4.d.3)
1.30mi
Number of structures placed in channel (C.4.d.7)
89.00
Pools Created through channel structure placement (C.4.d.5)
15.00