Raging River Preston Reach Rest./Acq.
#07-MPR-004 #07-MPR-004
Organization Snohomish Basin Lead Entity
Sponsor King County Department of Natural Resources and Parks
Status Completed
Schedule Start Date: 3/1/2006 End Date: 9/27/2010
Category Category: Restoration
DESCRIPTION
In 1964, a levee was constructed along the Raging River, just downstream of the community of Preston. The levee disconnected the river from 7 acres of floodplain and confined it to a narrow, straight alignment. Prior to levee construction, the reach experienced frequent channel migration. Historic aerial photos show two distinct complex channel formations in 1937 and 1960. Since the 1960s, the channel has maintained a simple alignment. Specific impacts to aquatic habitat conditions include: Elimination of side channels, reducing spawning, rearing and refuge habitat Reduction in pool area, reducing rearing habitat Elimination of mature riparian vegetation, reducing LWD delivery, shading, and cover and An increase in substrate particle size resulting in reduced spawning area. This project restored habitat by removing the levee. Boulders were placed at the fringe of the floodplain to protect the toe of the county road. The boulders are designed to provide roughness that will reduce the water velocity, preventing the river from scouring the slope. The resulting restoration of river processes led to the reestablishment of prime spawning and rearing habitat in the reach.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested09/21/2005Recreation and Conservation Office (RCO)Salmon State Projects$320,000.00
Requested09/21/2005King County Department of Natural Resources and ParksMatch$492,115.00
Allocated02/16/2010Recreation and Conservation Office (RCO)Salmon Federal Projects$135,494.97
Allocated02/16/2010King County Department of Natural Resources and ParksMatch$208,372.21
Spent02/16/2010Recreation and Conservation Office (RCO)Salmon Federal Projects-$135,494.97
Spent02/16/2010King County Department of Natural Resources and ParksMatch-$208,372.21
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$343,867.00 $812,115.00 $343,867.18 $343,867.18 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Puget Sound, Snoqualmie River, Threatened
Chum-Pop (ESU):Chum-Puget Sound/Strait of Georgia, Not Warranted
Coho-Pop (ESU):Coho-Puget Sound/Strait of Georgia, Species of Concern
County:King
HUC12:Raging River (171100100402)
HUC8:Snoqualmie (17110010)
Lead Entity Area:Snohomish Basin
Legislative District:05
Pink-Pop (ESU):Pink-Odd Year, Not Warranted
Pink2-Pop (ESU):Pink-Even Year, Not Warranted
Puget Sound Action Areas:Whidbey Island
Salmon Recovery Regions:Puget Sound
Sections:22
Sections:33
Snohomish Strategy Group:Mainstem-primary restoration
Snohomish Subbasins:Raging River
Steelhead-Pop (ESU):Steelhead-Puget Sound, Snoqualmie River, Threatened
Township:T24NR07E
Watershed Administrative Unit:Raging River
WRIA:Snohomish
View project on a larger map
  APPLICATION FINAL 
RESTORATION METRICS
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
0.15mi0.15mi
Fish Passage Improvement    
*Miles Of Stream Made Accessible (SRFB) (C.2.b.1)
0.25mi
*Number of blockages / impediments / barriers impeding passage (C.2.b.4)
0.00
Square Miles Of streambed made accessible (C.2.b.2)
0.00sq mi
 Fish passage blockages removed or altered (C.2.c.1)    
Number of Blockages/Impediments/Barriers Removed/Altered (C.2.c.2)
4.00
Instream Habitat Project    
Total Miles Of Instream Habitat Treated (C.4.b)
0.50mi0.41mi
 Channel reconfiguration and connectivity (C.4.c.1)    
Acres Of Channel/Off-Channel Connected Or Added (C.4.c.5)
5.40acres
Instream Pools Created/Added (C.4.c.6)
12.00
Miles of Off-Channel Stream Created or Connected (C.4.c.4)
0.18mi
Miles of Stream Treated for channel reconfiguration and connectivity (C.4.c.3)
0.41mi
 Streambank stabilization (C.4.e.1)    
Miles of Streambank Stabilized (C.4.e.3)
0.30mi0.11mi
Riparian Habitat Project    
*Total Riparian Acres Treated (C.5.b.2)
5.40acres
*Total Riparian Miles Streambank Treated (C.5.b.1)
0.41mi
 Planting (C.5.c.1)    
Acres Planted in riparian (C.5.c.3)
1.80acres
 Riparian Plant removal / control (C.5.h.1)    
Acres of riparian treated for plant removal/control (C.5.h.3)
5.40acres