Organization | Snohomish Basin Lead Entity |
Sponsor | King County Department of Natural Resources and Parks |
Status | Completed |
Schedule | Start Date: 7/29/1999 End Date: 5/16/2001 |
Category | Category: Restoration |
Type | Date | Funding Org | Funding Program | Match | Amount |
---|---|---|---|---|---|
Requested | 07/19/1999 | Recreation and Conservation Office (RCO) | Salmon State Projects | $50,000.00 | |
Requested | 07/19/1999 | King County Department of Natural Resources and Parks | Match | $74,000.00 | |
Allocated | 05/16/2001 | Recreation and Conservation Office (RCO) | Salmon State Projects | $45,335.27 | |
Allocated | 05/16/2001 | King County Department of Natural Resources and Parks | Match | $67,096.21 | |
Spent | 05/16/2001 | Recreation and Conservation Office (RCO) | Salmon State Projects | -$45,335.27 | |
Spent | 05/16/2001 | King County Department of Natural Resources and Parks | Match | -$67,096.21 |
Grant Project Agreement Totals | Proposed | Requested | Allocated | Spent | Balance |
$310,000.00 | $124,000.00 | $112,431.48 | $112,431.48 | $0.00 |
Type | Date | Funding Org | Funding Program | Match | Amount |
---|
Other Funding Totals | Proposed | Requested | Allocated | Spent | Balance |
Grand Totals | Proposed | Requested | Allocated | Spent | Balance |
Chinook-Pop (ESU): | Chinook-Puget Sound, Snoqualmie River, Threatened |
Chum-Pop (ESU): | Chum-Puget Sound/Strait of Georgia, Not Warranted |
Coho-Pop (ESU): | Coho-Puget Sound/Strait of Georgia, Species of Concern |
County: | King |
HUC12: | Griffin Creek (171100100403) |
HUC8: | Snoqualmie (17110010) |
Lead Entity Area: | Snohomish Basin |
Legislative District: | 12 |
Pink-Pop (ESU): | Pink-Odd Year, Not Warranted |
Pink2-Pop (ESU): | Pink-Even Year, Not Warranted |
Puget Sound Action Areas: | Whidbey Island |
Salmon Recovery Regions: | Puget Sound |
Sections: | 28 |
Snohomish Strategy Group: | Headwaters-secondary restoration |
Snohomish Subbasins: | Griffin Creek |
Steelhead-Pop (ESU): | Steelhead-Puget Sound, Snoqualmie River, Threatened |
Township: | T25NR07E |
Watershed Administrative Unit: | Griffin Creek |
WRIA: | Snohomish |
APPLICATION | FINAL | ||||
RESTORATION METRICS | |||||
Miles of Stream and/or Shoreline Treated or Protected (C.0.b) | 0.05 | mi | 0.05 | mi | |
Riparian Habitat Project | |||||
*Total Riparian Acres Treated (C.5.b.2) | 2.30 | acres | 2.30 | acres | |
*Total Riparian Miles Streambank Treated (C.5.b.1) | 1.30 | mi | 1.30 | mi | |
Fencing (C.5.d.1) | |||||
Acres of Riparian Area Protected by fencing (C.5.d.3) | |||||
Miles of Fence Along Stream (C.5.d.2) | |||||
Planting (C.5.c.1) | |||||
Acres Planted in riparian (C.5.c.3) | |||||
Riparian Plant removal / control (C.5.h.1) | |||||
Acres of riparian treated for plant removal/control (C.5.h.3) | 4.00 | acres | 4.00 | acres | |
Wetland Project | |||||
Total Acres Of Wetland Area Treated (C.8.b) | |||||
Wetland improvement/ restoration (C.8.e.1) | |||||
Acres of wetland Improved/Restored (C.8.e.2) |