Fall City Floodplain Restoration
#2019-11-New #2019-11-New
Organization Snohomish Basin Lead Entity
Sponsor King County Water & Land Resources
Status Active
Schedule Start Date: 7/1/2021 End Date: 6/30/2027
Category Category: Restoration
DESCRIPTION

The project includes the construction of two large facility setback projects on the Snoqualmie River at Fall City (SAFC). These are two of the four high priority projects identified in the SRFB-funded SAFC Feasibility Report. These projects will connect with an adjacent Upper Carlson floodplain restoration project that King County implemented in 2014. The Haffner & Barfuse project is well into the design process, and final design and permitting are expected to be completed by the time of construction funding.

Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested02/28/2020King County Water & Land ResourcesMatch$926,471.00
Requested02/28/2020Recreation and Conservation Office (RCO)PSAR Large Capital Projects$5,250,000.00
Allocated07/01/2021King County Water & Land ResourcesMatch$926,471.00
Allocated07/01/2021Recreation and Conservation Office (RCO)PSAR Large Capital Projects$5,250,000.00
Spent05/20/2025King County Water & Land ResourcesMatch-$522,934.54
Spent05/20/2025Recreation and Conservation Office (RCO)PSAR Large Capital Projects-$2,963,294.43
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$15,000,000.00 $6,176,471.00 $6,176,471.00 $3,486,228.97 $2,690,242.03
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Allocated10/26/2023Department of Ecology (ECY)Floodplains by DesignMatch$10,309,278.00
Other Funding Totals Proposed Requested Allocated Spent Balance
$0.00 $0.00 $10,309,278.00 $0.00 $10,309,278.00
Grand Totals Proposed Requested Allocated Spent Balance
$15,000,000.00 $6,176,471.00 $16,485,749.00 $3,486,228.97 $12,999,520.03
PRIMARY SPONSOR
PROJECT CONTACT
ALT PROJECT CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Puget Sound, Snoqualmie River, Threatened
Chum-Pop (ESU):Chum-Puget Sound/Strait of Georgia, Not Warranted
Coho-Pop (ESU):Coho-Puget Sound/Strait of Georgia, Species of Concern
County:King
HUC12:Patterson Creek-Snoqualmie River (171100100404)
HUC8:Snoqualmie (17110010)
Lead Entity Area:Snohomish Basin
Legislative District:12
Pink-Pop (ESU):Pink-Odd Year, Not Warranted
Pink2-Pop (ESU):Pink-Even Year, Not Warranted
Puget Sound Action Areas:Whidbey Island
Salmon Recovery Regions:Puget Sound
Sections:10
Snohomish Strategy Group:Mainstem-primary restoration
Snohomish Subbasins:Upper Mainstem Snoqualmie
Steelhead-Pop (ESU):Steelhead-Puget Sound, Snoqualmie River, Threatened
Township:T24NR07E
Watershed Administrative Unit:Patterson Creek
WRIA:Snohomish
View project on a larger map

Related Projects

  APPLICATION FINAL 
RESTORATION METRICS
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
1.91mi
Instream Habitat Project    
Total Miles Of Instream Habitat Treated (C.4.b)
1.91mi
 Channel reconfiguration and connectivity (C.4.c.1)    
Acres Of Channel/Off-Channel Connected Or Added (C.4.c.5)
145.00acres
Instream Pools Created/Added (C.4.c.6)
0.00
Miles of Off-Channel Stream Created or Connected (C.4.c.4)
0.85mi
Miles of Stream Treated for channel reconfiguration and connectivity (C.4.c.3)
1.91mi
 Channel structure placement (C.4.d.1)    
Miles of Stream Treated for channel structure placement (C.4.d.3)
0.16mi
Number of structures placed in channel (C.4.d.7)
4.00
Pools Created through channel structure placement (C.4.d.5)
0.00
 Streambank stabilization (C.4.e.1)    
Miles of Streambank Stabilized (C.4.e.3)
0.30mi
Upland Habitat And Sediment Project    
Acres of Upland Habitat Area Treated (C.6.b.1)
0.80acres
Miles of Road Treated (C.6.b.2)
0.30mi
 Road abandonment (C.6.d.1)    
Miles of Road Abandoned (C.6.d.2)
0.30mi