SnoCo Beach Nourishment Const
#07-NR-028 #07-NR-028
Organization Snohomish Basin Lead Entity
Sponsor Snohomish County Public Works
Status Completed
Schedule Start Date: 12/5/2013 End Date: 4/28/2017
Category Category: Restoration
Project Photo
DESCRIPTION
The Snohomish County Beach Nourishment Project is located adjacent to the railroad impounded shoreline in WRIA 7 between Mukilteo and Everett in Snohomish County. Identified through a stakeholder process and supported by a technical review, this project will place sediment at three locations adjacent to stream deltas along the 4.5 mile drift cell. At the City of Everett's Howarth Park site, in addition to sediment placement, existing riprap bank protection and associated fill will be removed from the beach to expand the beach and improve public access to one of only two city saltwater parks. The goal of this restoration project is to improve the quality of nearshore habitat along the 4.5 mile project reach by augmenting the supply of finer sediments to the upper intertidal zone. Providing clean, appropriately sized sediments throughout the drift cell should significantly improve salmon productivity and juvenile capacity and is a "most pressing need" in the Snohomish Basin Salmon Recovery 3-yr work plan. The primary species supported by these nearshore habitats are Chinook Salmon, Pacific Sand Lance, and Surf Smelt. A key element of this proposal is the framework developed whereby the City of Everett, the Port of Everett, the Washington State Department of Natural Resources, Snohomish County and the U.S. Army Corps of Engineers are working to ensure the long-term beneficial use of the dredge material from the Snohomish River along this drift cell.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested08/02/2013Recreation and Conservation Office (RCO)Salmon State Projects$298,764.00
Requested08/02/2013Snohomish County Public WorksMatch$600,000.00
Allocated04/28/2017Recreation and Conservation Office (RCO)Salmon State Projects$188,589.00
Allocated04/28/2017Recreation and Conservation Office (RCO)Estuary & Salmon Restoration$240,000.00
Allocated04/28/2017Recreation and Conservation Office (RCO)Puget Sound Acq. & Restoration$383,456.63
Allocated04/28/2017Recreation and Conservation Office (RCO)ESRP-EPA Marine & Nearshore$600,000.00
Spent12/07/2016Recreation and Conservation Office (RCO)Salmon State Projects-$188,589.00
Spent12/07/2016Recreation and Conservation Office (RCO)Estuary & Salmon Restoration-$240,000.00
Spent12/07/2016Recreation and Conservation Office (RCO)ESRP-EPA Marine & Nearshore-$600,000.00
Spent04/07/2017Snohomish County Public WorksMatch-$0.00
Spent04/07/2017Recreation and Conservation Office (RCO)Puget Sound Acq. & Restoration-$383,456.63
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$1,635,000.00 $898,764.00 $1,412,045.63 $1,412,045.63 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Requested11/19/2012City of EverettMatch$40,000.00
Requested11/19/2012Port of EverettMatch$187,800.00
Requested03/18/2013US Fish & Wildlife Service (USFWS)Match$50,000.00
Allocated11/19/2012City of EverettMatch$40,000.00
Allocated11/19/2012Port of EverettMatch$187,800.00
Allocated03/18/2013US Fish & Wildlife Service (USFWS)Match$50,000.00
Spent11/19/2012City of EverettMatch-$40,000.00
Spent11/19/2012Port of EverettMatch-$187,800.00
Spent03/18/2013US Fish & Wildlife Service (USFWS)Match-$50,000.00
Other Funding Totals Proposed Requested Allocated Spent Balance
$0.00 $277,800.00 $277,800.00 $277,800.00 $0.00
Grand Totals Proposed Requested Allocated Spent Balance
$1,635,000.00 $1,176,564.00 $1,689,845.63 $1,689,845.63 $0.00
PRIMARY SPONSOR
PROJECT CONTACT
SECONDARY SPONSOR
ALT PROJECT CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Puget Sound, Threatened
Chum-Pop (ESU):Chum-Puget Sound/Strait of Georgia, Not Warranted
City Areas:Everett
Coho-Pop (ESU):Coho-Puget Sound/Strait of Georgia, Species of Concern
County:Snohomish
HUC12:Powder Mill Gulch-Frontal Possession Sound (171100190202)
HUC12:Skagit Bay (171100191100)
HUC8:Puget Sound (17110019)
Lead Entity Area:Snohomish Basin
Legislative District:38
Pink-Pop (ESU):Pink-Odd Year, Not Warranted
Puget Sound Action Areas:Whidbey Island
Salmon Recovery Regions:Puget Sound
Sections:25
Sections:34
Sections:35
Sections:36
Skagit Tiers:Tier 2 Pocket Estuaries
Snohomish Strategy Group:Urban stream restoration
Snohomish Subbasins:Everett Drainages
Steelhead-Pop (ESU):Steelhead-Puget Sound, Snohomish/Skykomish Rivers, Threatened
Steelhead-Pop (ESU):Steelhead-Puget Sound, Threatened
Township:T29NR04E
Watershed Administrative Unit:Everett
WRIA:Snohomish
View project on a larger map

Related Projects

  APPLICATION FINAL 
RESTORATION METRICS
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
0.00mi0.00mi
Estuarine / Nearshore Project    
*Total Amount Of Estuarine / Nearshore Acres Treated (C.9.b)
2.40acres2.40acres
 Beach nourishment (C.9.l.1)    
Acres Treated for beach nourishment (C.9.l.4)
2.40acres2.40acres
Cubic Yards Of Beach Substrate Placed (C.9.l.2)
26,767.00cubic yds
Miles of Shoreline Treated for beach nourishment (C.9.l.3)
0.85mi0.85mi
 Estuarine planting or native plant establishment (C.9.r.1)    
Acres of Estuarine planting or native plant establishment (C.9.r.3)
0.50acres
 Shoreline armor removal or modification (C.9.k.1)    
Acres of Shoreline Treated for armor modification/removal (C.9.k.3)
0.40acres0.40acres
Miles of Shoreline Treated for armor modification/removal (C.9.k.2)
0.08mi0.08mi
ADDITIONAL INFORMATION