Organization | Green/Duwamish and Central Puget Sound Watershed (WRIA 9) Lead Entity |
Sponsor | Burien Parks & Recreation Department |
Status | Completed |
Schedule | Start Date: 12/10/2009 End Date: 3/21/2016 |
Category | Category: Restoration |
Type | Date | Funding Org | Funding Program | Match | Amount |
---|---|---|---|---|---|
Requested | 08/28/2009 | Burien Parks & Recreation Department | Match | $133,000.00 | |
Requested | 08/28/2009 | Recreation and Conservation Office (RCO) | Puget Sound Acq. & Restoration | $750,000.00 | |
Allocated | 03/21/2016 | Burien Parks & Recreation Department | Match | $131,745.74 | |
Allocated | 03/21/2016 | Recreation and Conservation Office (RCO) | ESRP-EPA Marine & Nearshore | $607,567.00 | |
Allocated | 03/21/2016 | Recreation and Conservation Office (RCO) | Puget Sound Acq. & Restoration | $750,000.00 | |
Allocated | 03/21/2016 | Recreation and Conservation Office (RCO) | PSAR Large Capital Projects | $2,777,806.00 | |
Spent | 07/18/2013 | Recreation and Conservation Office (RCO) | Puget Sound Acq. & Restoration | -$750,000.00 | |
Spent | 11/14/2013 | Recreation and Conservation Office (RCO) | ESRP-EPA Marine & Nearshore | -$607,567.00 | |
Spent | 10/08/2014 | Burien Parks & Recreation Department | Match | -$131,745.74 | |
Spent | 10/08/2014 | Recreation and Conservation Office (RCO) | PSAR Large Capital Projects | -$2,777,806.00 |
Grant Project Agreement Totals | Proposed | Requested | Allocated | Spent | Balance |
$7,500,000.00 | $883,000.00 | $4,267,118.74 | $4,267,118.74 | $0.00 |
Type | Date | Funding Org | Funding Program | Match | Amount |
---|
Other Funding Totals | Proposed | Requested | Allocated | Spent | Balance |
Grand Totals | Proposed | Requested | Allocated | Spent | Balance |
Seahurst Park after phase two completion.
Chinook-Pop (ESU): | Chinook-Puget Sound, Threatened |
Chum-Pop (ESU): | Chum-Puget Sound/Strait of Georgia, Not Warranted |
City Areas: | Burien |
Coho-Pop (ESU): | Coho-Puget Sound/Strait of Georgia, Species of Concern |
County: | King |
HUC12: | Miller Creek-Frontal East Passage (171100190204) |
HUC12: | Puget Sound (171100191200) |
HUC8: | Puget Sound (17110019) |
Lead Entity Area: | Green/Duwamish/Central Puget Sound Watershed (WRIA 9) |
Legislative District: | 34 |
Pink-Pop (ESU): | Pink-Odd Year, Not Warranted |
Puget Sound Action Areas: | South Central Puget Sound |
Salmon Recovery Regions: | Puget Sound |
Sections: | 13 |
Steelhead-Pop (ESU): | Steelhead-Puget Sound, Green River, Threatened |
Steelhead-Pop (ESU): | Steelhead-Puget Sound, Threatened |
Township: | T23NR03E |
Watershed Administrative Unit: | S Elliott Bay/E Passage |
WRIA: | Duwamish - Green |
APPLICATION | FINAL | ||||
RESTORATION METRICS | |||||
Miles of Stream and/or Shoreline Treated or Protected (C.0.b) | 0.04 | mi | 0.04 | mi | |
Estuarine / Nearshore Project | |||||
*Total Amount Of Estuarine / Nearshore Acres Treated (C.9.b) | 6.00 | acres | 6.00 | acres | |
Beach nourishment (C.9.l.1) | |||||
Acres Treated for beach nourishment (C.9.l.4) | 3.00 | acres | |||
Cubic Yards Of Beach Substrate Placed (C.9.l.2) | 22,000.00 | cubic yds | |||
Miles of Shoreline Treated for beach nourishment (C.9.l.3) | 0.53 | mi | |||
Regrading of slope (C.9.i.1) | |||||
Acres of Estuary Treated through slope regrading (C.9.i.2) | 5.50 | acres | |||
Removal of existing fill material (C.9.g.1) | |||||
Acres of Estuary Treated through fill material removal (C.9.g.2) | 5.50 | acres | |||
Shoreline armor removal or modification (C.9.k.1) | |||||
Acres of Shoreline Treated for armor modification/removal (C.9.k.3) | 6.00 | acres | |||
Miles of Shoreline Treated for armor modification/removal (C.9.k.2) | 0.53 | mi | |||
Riparian Habitat Project | |||||
*Total Riparian Acres Treated (C.5.b.2) | 2.00 | acres | |||
*Total Riparian Miles Streambank Treated (C.5.b.1) | 0.01 | mi | |||
Planting (C.5.c.1) | |||||
Acres Planted in riparian (C.5.c.3) | 2.00 | acres | |||
Riparian Plant removal / control (C.5.h.1) | |||||
Acres of riparian treated for plant removal/control (C.5.h.3) | 2.00 | acres |