Kelsey Creek Reach 2- Man-made secondary channel/ channel improvements
#N461 #N461
 Tier 2 Kelsey Creek Kelsey Creek Reach 2- Man-made secondary channel/ channel improvements
Organization Lake Washington/Cedar/Sammamish Watershed (WRIA 8) Lead Entity
Sponsor City of Bellevue
Status Completed
Schedule Start Date: 1/1/2005 End Date: 12/31/2014
Category Category: Restoration
DESCRIPTION

Stream Channel Improvements: If berm on reach 76-05 cannot be moved, then explore opportunities to utilize man-made tributary through pastures as secondary channel. Improve buffers around tributary with native vegetation and fencing.

End date not confirmed.

Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
PHOTOS

 
View project on a larger map