Cedar River/Taylor Creek Confluence
#00-1074 #00-1074
Organization Lake Washington/Cedar/Sammamish Watershed (WRIA 8) Lead Entity
Sponsor King County Water & Land Resources
Status Completed
Schedule Start Date: 3/17/2000 End Date: 2/6/2004
Category Category: Acquisition
DESCRIPTION
The Lower Cedar River watershed is located in southeastern King County and covers 66 square miles including 20 miles of river. It provides over half the fresh water inflow to Lake Washington, and for its size, it supports one of the largest salmon populations in the state including sockeye, coho, steelhead, and ESA-listed Chinook. The Draft State/Tribal Plan for WRIA 8 calls the Cedar River and Bear Creek populations of Chinook "the healthiest naturally spawning population in the (Greater Lake Washington) watershed." King County used this funding to acquire approximately 9.14 acres of forested riparian floodplain on the Cedar River mainstream including 1,000 feet of mainstream channel, nearly 1,300 feet of the lowermost reach and the mouth of Taylor Creek, and one of the largest remaining floodplain wetlands adjacent to the mainstream. Additionally, directly across the river is a 13-acre forested floodplain and side channel acquisition site. About 500 feet upriver there is a project that involves setting back the levee, bioengineering the levee face and creating groundwater-fed spawning habitat. About 800 feet upstream of Taylor Creek there is a project that would alleviate long-standing flooding and improve habitat and water quality in Taylor Creek. This site was selected by the Cedar River Council in 1999 as a top priority for protection under the Cedar River Legacy program, which was initiated in 1994 and has protected over 400 acres of habitat in the lower Cedar River.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested02/03/2000King County Water & Land ResourcesMatch$30,272.00
Requested02/03/2000Recreation and Conservation Office (RCO)Salmon State Projects$170,000.00
Allocated03/17/2000King County Water & Land ResourcesMatch$30,272.00
Allocated03/17/2000Recreation and Conservation Office (RCO)Salmon State Projects$170,000.00
Spent01/27/2004King County Water & Land ResourcesMatch-$30,272.00
Spent01/27/2004Recreation and Conservation Office (RCO)Salmon State Projects-$170,000.00
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$200,272.00 $200,272.00 $200,272.00 $200,272.00 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Puget Sound, Cedar River, Threatened
Chum-Pop (ESU):Chum-Puget Sound/Strait of Georgia, Not Warranted
City Areas:Hobart
Coho-Pop (ESU):Coho-Puget Sound/Strait of Georgia, Species of Concern
County:King
HUC12:Madsen Creek-Cedar River (171100120107)
HUC8:Lake Washington (17110012)
Lead Entity Area:Lake Washington/Cedar/Sammamish Watershed (WRIA 8)
Legislative District:05
Pink-Pop (ESU):Pink-Odd Year, Not Warranted
Puget Sound Action Areas:South Central Puget Sound
Salmon Recovery Regions:Puget Sound
Sections:04
Steelhead-Pop (ESU):Steelhead-Puget Sound, Cedar River, Threatened
Township:T22NR06E
Watershed Administrative Unit:Lower Cedar River
WRIA:Cedar - Sammamish
View project on a larger map
  APPLICATION FINAL 
ACQUISTION METRICS
Real Property Acquisition    
Miles of Streambank and/or Shoreline Protected by Land or Easement Acquisition
0.25mi
 Land    
Acres by Acreage Type (fee simple)
Wetlands
9.14
Total
9.14
acres
 
WORKSITE METRICS
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
0.00mi0.25mi
Real Property Acquisition    
 Acquisition or lease of land, wetland or estuarine for conservation (C.10.c.1)    
Acres Of Land, Wetland Or Estuarine Area Conserved By Acquisition Or Lease (C.10.c.6)
Miles Of Streambank Protected By Land or Easement Acquisition (C.10.c.5)