Titlow - Armor Removal and Shoreline Restoration
#15-1447 #15-1447
 WRIA 12 Titlow Estuary Titlow - Armor Removal and Shoreline Restoration
Organization Puyallup and Chambers Watershed Salmon Recovery Lead Entity
Sponsor South Puget Sound Salmon Enhancement Group (SPSSEG)
Status Completed
Schedule Start Date: 6/1/2015 End Date: 4/21/2017
Category Category: Restoration
Project Photo
DESCRIPTION
This project advanced shoreline restoration objectives within Titlow Park with the removal of a house (Kay's house), seawall, boat house, and rip rap armor from the shoreline to north of the Titlow Lagoon in the Tacoma Narrows. The project also removed lead and arsenic contaminated soils from the 1 acre project site. Overall the project restored 150 linear feet, daylighted 750 square feet of back beach that was truncated by the armor and fill, reduced beach sediment grain size for forage fish spawning, and connects to continuous natural beach-bluff habitat reaching to the north within the park.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested07/28/2015Recreation and Conservation Office (RCO)ESRP-EPA Marine & Nearshore$522,000.00
Allocated11/29/2017Recreation and Conservation Office (RCO)Marine Shoreline Protection$37,290.25
Allocated11/29/2017Recreation and Conservation Office (RCO)ESRP-EPA Marine & Nearshore$548,898.66
SpentRecreation and Conservation Office (RCO)Marine Shoreline Protection-$37,290.25
Spent04/03/2017Recreation and Conservation Office (RCO)Salmon State Projects-$0.00
Spent09/19/2017South Puget Sound Salmon Enhancement Group (SPSSEG)Match-$0.00
Spent09/19/2017Recreation and Conservation Office (RCO)ESRP-EPA Marine & Nearshore-$548,898.66
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$649,000.00 $522,000.00 $586,188.91 $586,188.91 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
ALT PROJECT CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Puget Sound, Threatened
Chum-Pop (ESU):Chum-Puget Sound/Strait of Georgia, Not Warranted
Coho-Pop (ESU):Coho-Puget Sound/Strait of Georgia, Species of Concern
County:Pierce
HUC12:South Puget Sound (171100190900)
HUC8:Puget Sound (17110019)
Lead Entity Area:Pierce County
Legislative District:27
Pink-Pop (ESU):Pink-Odd Year, Not Warranted
Puget Sound Action Areas:South Puget Sound
Salmon Recovery Regions:Puget Sound
Steelhead-Pop (ESU):Steelhead-Puget Sound, Threatened
Watershed Administrative Unit:Chambers-Clover
WRIA:Chambers - Clover
View project on a larger map

Related Projects

  APPLICATION FINAL 
RESTORATION METRICS
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
0.03mi0.03mi
Estuarine / Nearshore Project    
*Total Amount Of Estuarine / Nearshore Acres Treated (C.9.b)
0.40acres0.40acres
 Beach nourishment (C.9.l.1)    
Acres Treated for beach nourishment (C.9.l.4)
0.10acres0.10acres
Cubic Yards Of Beach Substrate Placed (C.9.l.2)
0.00cubic yds
Miles of Shoreline Treated for beach nourishment (C.9.l.3)
0.01mi0.01mi
 Contaminant removal / remediation (C.9.m.1)    
Acres Treated for contaminant removal/modification (C.9.m.2)
0.40acres0.40acres
 Shoreline armor removal or modification (C.9.k.1)    
Acres of Shoreline Treated for armor modification/removal (C.9.k.3)
0.40acres0.40acres
Miles of Shoreline Treated for armor modification/removal (C.9.k.2)
0.03mi0.03mi
Riparian Habitat Project    
*Total Riparian Acres Treated (C.5.b.2)
0.40acres0.40acres
*Total Riparian Miles Streambank Treated (C.5.b.1)
0.03mi0.03mi
 Debris/structures removal (C.5.j.1)    
Acres of Riparian Area Treated. (C.5.j.2)
0.40acres0.40acres
 Planting (C.5.c.1)    
Acres Planted in riparian (C.5.c.3)
0.20acres0.20acres
Miles of streambank planted (C.5.c.4)
0.01mi0.01mi
ADDITIONAL INFORMATION