Middle Boise Creek Restoration
#10-1859 #10-1859
 WRIA 10 Boise Creek Middle Boise Creek Restoration
Organization Puyallup and Chambers Watershed Salmon Recovery Lead Entity
Sponsor King County Department of Natural Resources and Parks
Status Completed
Schedule Start Date: 12/10/2010 End Date: 4/30/2014
Category Category: Restoration
DESCRIPTION
King County designed, permitted, and constructed a habitat restoration project on Boise Creek in a predominantly agricultural area. Historic stream and floodplain drainage activities have included extensive stream channelization, channel dredging, and placement of drain tiles to expand agricultural areas. This has resulted in channel entrenchment, gravel embedment, sidecast spoil terraces, and the removal of riparian vegetation and instream wood. King County is completing a feasibility analysis and conceptual design for future restoration projects to be implemented along Boise Creek from River Mile 1 to 3. King County completed: a) a permit-ready design; b) construction of a streambank restoration pilot project; and c) riparian restoration. Acquisition of property was paid for by King County outside of this grant. King County will monitor the project and maintain the project for at least five years following construction. The goal of this project is to restore fish habitat (in particular, slow water margin habitat) and improve water quality in a degraded reach of Boise Creek. Specific objectives are to: a) place wood in the riparian zone, including the stream; and b) revegetate the riparian zone with native trees and shrubs. This project significantly benefitted Chinook and steelhead, and in particular White River spring Chinook, which spawn and rear in Boise Creek. They are the only spring population in south Puget Sound and are genetically the most distinctive stock in south and central Puget Sound. Approximately one mile of livestock exclusion fencing was installed.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested08/20/2010King County Department of Natural Resources and ParksMatch$48,000.00
Requested08/20/2010Recreation and Conservation Office (RCO)Salmon State Projects$113,705.00
Allocated09/27/2012King County Department of Natural Resources and ParksMatch$48,000.00
Allocated09/27/2012Recreation and Conservation Office (RCO)Salmon Federal Projects$113,705.00
Spent04/30/2014King County Department of Natural Resources and ParksMatch-$48,000.00
Spent04/30/2014Recreation and Conservation Office (RCO)Salmon Federal Projects-$113,705.00
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$161,705.00 $161,705.00 $161,705.00 $161,705.00 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Puget Sound, White River, Threatened
Chum-Pop (ESU):Chum-Puget Sound/Strait of Georgia, Not Warranted
Coho-Pop (ESU):Coho-Puget Sound/Strait of Georgia, Species of Concern
County:King
HUC12:Boise Creek-White River (171100140403)
HUC8:Puyallup (17110014)
Lead Entity Area:Pierce County
Legislative District:05
Pink-Pop (ESU):Pink-Odd Year, Not Warranted
Puget Sound Action Areas:South Central Puget Sound
Salmon Recovery Regions:Puget Sound
Sections:25
Sections:36
Steelhead-Pop (ESU):Steelhead-Puget Sound, White River, Threatened
Township:T20NR06E
Watershed Administrative Unit:Mud Mtn
WRIA:Puyallup - White
View project on a larger map

Related Projects

  APPLICATION FINAL 
RESTORATION METRICS
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
0.09mi0.09mi
Instream Habitat Project    
Total Miles Of Instream Habitat Treated (C.4.b)
0.00mi0.09mi
 Channel reconfiguration and connectivity (C.4.c.1)    
Acres Of Channel/Off-Channel Connected Or Added (C.4.c.5)
0.50acres
Instream Pools Created/Added (C.4.c.6)
0.00
Miles of Off-Channel Stream Created or Connected (C.4.c.4)
0.09mi
Miles of Stream Treated for channel reconfiguration and connectivity (C.4.c.3)
0.09mi
 Channel structure placement (C.4.d.1)    
Acres Of Streambed Treated for channel structure placement (C.4.d.4)
0.00acres0.10acres
Miles of Stream Treated for channel structure placement (C.4.d.3)
0.00mi0.09mi
Number of structures placed in channel (C.4.d.7)
0.0010.00
Pools Created through channel structure placement (C.4.d.5)
0.000.00
Yards Of Average Stream-Width At Mid-Point Of Worksite (C.4.d.6)
0.00yd7.00yd
Riparian Habitat Project    
*Total Riparian Acres Treated (C.5.b.2)
0.50acres0.50acres
*Total Riparian Miles Streambank Treated (C.5.b.1)
0.09mi0.09mi
 Fencing (C.5.d.1)    
Acres of Riparian Area Protected by fencing (C.5.d.3)
0.50acres0.50acres
Miles of Fence Along Stream (C.5.d.2)
0.09mi0.09mi
 Planting (C.5.c.1)    
Acres Planted in riparian (C.5.c.3)
0.50acres0.50acres
ADDITIONAL INFORMATION