DESCRIPTION
This project restored a 12.85-acre site along the mainstem of South Prairie Creek at RM 3.7 (west of South Prairie, WA), including the lower 1600 feet of an important cold-water tributary, South Silver Springs, which flows through the site. The project removed floodplain fill and a concrete weir on South Silver Springs; constructed 800 feet of new stream channel and 370 feet of off channel alcoves on South Silver Springs in the vicinity of where the fill was removed; controlled invasive vegetation; placed wood throughout the new South Silver Springs channel and in South Prairie Creek for use by rearing juvenile and adult salmon spawners; removed approximately 300' of riprap along South Prairie Creek; and revegetated the site. The project primarily benefits juvenile salmonids by providing enhanced rearing habitat, high-flow refuge, and improved connectivity between the tributary and mainstem creek. Adult salmon also benefit by the enhancement of some spawning areas in the tributary and placement of wood into the mainstem for cover. Large numbers of juvenile coho have been seen entering South Silver Springs within the first few months following construction. Pink, coho and chum salmon adults have already spawned in the new channel as documented by tribal surveys. No future activities are expected at this site except for maintenance of plants. Once a native forest has matured it should provide long term natural maintenance.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested09/08/2008Pierce County Planning and Public Works SWMMatch$80,800.00
Requested09/08/2008Recreation and Conservation Office (RCO)Salmon State Projects$325,000.00
Allocated12/11/2008Pierce County Planning and Public Works SWMMatch$80,800.00
Allocated12/11/2008Recreation and Conservation Office (RCO)Salmon Federal Projects$325,000.00
Spent08/16/2013Pierce County Planning and Public Works SWMMatch-$80,800.00
Spent08/16/2013Recreation and Conservation Office (RCO)Salmon Federal Projects-$325,000.00
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$405,800.00 $405,800.00 $405,800.00 $405,800.00 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Puget Sound, Puyallup River, Threatened
Chum-Pop (ESU):Chum-Puget Sound/Strait of Georgia, Not Warranted
City Areas:Prairie Ridge
Coho-Pop (ESU):Coho-Puget Sound/Strait of Georgia, Species of Concern
County:Pierce
HUC12:South Prairie Creek (171100140104)
HUC8:Puyallup (17110014)
Lead Entity Area:Pierce County
Legislative District:31
Pink-Pop (ESU):Pink-Odd Year, Not Warranted
Puget Sound Action Areas:South Central Puget Sound
Salmon Recovery Regions:Puget Sound
Sections:14
Steelhead-Pop (ESU):Steelhead-Puget Sound, Puyallup River/Carbon River, Threatened
Township:T19NR05E
Watershed Administrative Unit:South Prairie
WRIA:Puyallup - White
View project on a larger map
  APPLICATION FINAL 
RESTORATION METRICS
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
0.30mi0.50mi
Instream Habitat Project    
Total Miles Of Instream Habitat Treated (C.4.b)
0.50mi0.50mi
 Channel reconfiguration and connectivity (C.4.c.1)    
Acres Of Channel/Off-Channel Connected Or Added (C.4.c.5)
0.50acres
Instream Pools Created/Added (C.4.c.6)
3.00
Miles of Off-Channel Stream Created or Connected (C.4.c.4)
0.25mi
Miles of Stream Treated for channel reconfiguration and connectivity (C.4.c.3)
0.50mi
 Channel structure placement (C.4.d.1)    
Acres Of Streambed Treated for channel structure placement (C.4.d.4)
0.10acres
Miles of Stream Treated for channel structure placement (C.4.d.3)
0.10mi
Number of structures placed in channel (C.4.d.7)
50.00
Pools Created through channel structure placement (C.4.d.5)
3.00
Yards Of Average Stream-Width At Mid-Point Of Worksite (C.4.d.6)
3.00yd
Riparian Habitat Project    
*Total Riparian Acres Treated (C.5.b.2)
13.00acres
*Total Riparian Miles Streambank Treated (C.5.b.1)
0.50mi
 Planting (C.5.c.1)    
Acres Planted in riparian (C.5.c.3)
8.00acres
 Riparian Plant removal / control (C.5.h.1)    
Acres of riparian treated for plant removal/control (C.5.h.3)
13.00acres