Organization | Nisqually River Salmon Recovery Lead Entity |
Sponsor | Nisqually Land Trust |
Status | Completed |
Schedule | Start Date: 9/23/2021 End Date: 11/20/2023 |
Category | Category: Acquisition |
In preparation for the next phase of the Lower Ohop Creek Restoration Project, the Land Trust proposes to pursue permanent protection of properties throughout the portion of the Lower Ohop Creek Restoration project envelope where restoration activities have not yet taken place. The Land Trust will work with willing landowners to acquire up to 142 acres in the Lower Ohop Valley as a part of this project. Acquisition of these properties will allow restoration partners to maximize instream, floodplain, and riparian habitat improvements in this part of the valley. This project is designed to provide an opportunity for acquisition of up to five properties in the project area, but at a minimum will include acquisition of the two properties described below.
Property A includes 0.2 mile of Ohop Creek shoreline, and approximately 10 acres of floodplain in the Lower Ohop Creek Restoration area. The proposed acquisition is an undeveloped portion of a developed rural residential parcel that is zoned rural 10.
Property B includes 0.1 mile of Ohop Creek shoreline, and approximately 1.4 acres of floodplain in the Lower Ohop Creek Restoration area. The proposed acquisition is an undeveloped portion of a developed rural residential parcel that is zoned rural 10.
Type | Date | Funding Org | Funding Program | Match | Amount |
---|---|---|---|---|---|
Requested | 02/10/2021 | Nisqually Land Trust | Match | $22,950.00 | |
Requested | 02/10/2021 | Recreation and Conservation Office (RCO) | Salmon State Projects | $130,000.00 | |
Allocated | 11/20/2023 | Nisqually Land Trust | Match | $1,611.48 | |
Allocated | 11/20/2023 | Recreation and Conservation Office (RCO) | Salmon Federal Projects | $9,128.23 | |
Spent | 11/20/2023 | Nisqually Land Trust | Match | -$1,611.48 | |
Spent | 11/20/2023 | Recreation and Conservation Office (RCO) | Salmon Federal Projects | -$9,128.23 |
Grant Project Agreement Totals | Proposed | Requested | Allocated | Spent | Balance |
$152,590.00 | $152,950.00 | $10,739.71 | $10,739.71 | $0.00 |
Type | Date | Funding Org | Funding Program | Match | Amount |
---|
Other Funding Totals | Proposed | Requested | Allocated | Spent | Balance |
Grand Totals | Proposed | Requested | Allocated | Spent | Balance |
Chinook-Pop (ESU): | Chinook-Puget Sound, Nisqually River, Threatened |
Chum-Pop (ESU): | Chum-Puget Sound/Strait of Georgia, Not Warranted |
Coho-Pop (ESU): | Coho-Puget Sound/Strait of Georgia, Species of Concern |
County: | Pierce |
HUC12: | Ohop Creek (171100150203) |
HUC8: | Nisqually (17110015) |
Lead Entity Area: | Nisqually River |
Legislative District: | 02 |
Pink-Pop (ESU): | Pink-Odd Year, Not Warranted |
Puget Sound Action Areas: | South Puget Sound |
Salmon Recovery Regions: | Puget Sound |
Sections: | 17 |
Steelhead-Pop (ESU): | Steelhead-Puget Sound, Nisqually River, Threatened |
Township: | T16NR04E |
Watershed Administrative Unit: | Ohop Creek |
WRIA: | Nisqually |
APPLICATION | FINAL | ||||
ACQUISTION METRICS | |||||
Real Property Acquisition | |||||
Miles of Streambank and/or Shoreline Protected by Land or Easement Acquisition | 0.20 | mi | 0.20 | mi | |
Land | |||||
Acres by Acreage Type (fee simple) | Wetlands 10.00 Total 10.00 | acres | Wetlands 10.43 Total 10.43 | acres | |
WORKSITE METRICS | |||||
Miles of Stream and/or Shoreline Treated or Protected (C.0.b) | 0.30 | mi | 0.20 | mi |