Nisqually/Powell Protection &Restoration
#11-POWELL-1002 #11-POWELL-1002
Organization Nisqually River Salmon Recovery Lead Entity
Sponsor Nisqually Land Trust
Status Completed
Schedule Start Date: 4/1/2005 End Date: 7/21/2009
Category Category: Acquisition & Restoration
DESCRIPTION
Nisqually Land Trust used this funding to permanently protect 239 acres on the Nisqually River. The property included Powell Creek and associated floodplain wetland. The confluence of the Nisqually and Powell Creek wetland complex is the most substantial such off-channel habitat complex on the Nisqually. Insuring their permanent protection was a very substantial action. Following acquisition, restoration actons included removing culverts on Powell Creek drains. Removing them restored connectivity to the single largest off-channel complex in the entire Nisqually River Basin. The restoration project opened up three miles of habitat and provides spawning and rearing habitat for coho, Chinook, steelhead, cutthroat, and possibly chum. The Powell Creek site was selected for early action restoration in the Nisqually River Off-Channel Habitat Assessment.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested07/19/2004Recreation and Conservation Office (RCO)Salmon State Projects$596,566.00
Requested07/19/2004Nisqually Land TrustMatch$700,000.00
Allocated12/03/2004Recreation and Conservation Office (RCO)Salmon Federal Projects$596,566.00
Allocated12/03/2004Nisqually Land TrustMatch$700,000.00
Spent07/21/2009Recreation and Conservation Office (RCO)Salmon Federal Projects-$596,566.00
Spent07/21/2009Nisqually Land TrustMatch-$700,000.00
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$1,296,566.00 $1,296,566.00 $1,296,566.00 $1,296,566.00 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
ALT PROJECT CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Puget Sound, Nisqually River, Threatened
Chum-Pop (ESU):Chum-Puget Sound/Strait of Georgia, Not Warranted
Coho-Pop (ESU):Coho-Puget Sound/Strait of Georgia, Species of Concern
County:Pierce
County:Thurston
HUC12:Powell Creek-Nisqually River (171100150205)
HUC8:Nisqually (17110015)
Lead Entity Area:Nisqually River
Legislative District:02
Pink-Pop (ESU):Pink-Odd Year, Not Warranted
Puget Sound Action Areas:South Puget Sound
Salmon Recovery Regions:Puget Sound
Sections:20
Sections:21
Sections:27
Sections:28
Sections:29
Steelhead-Pop (ESU):Steelhead-Puget Sound, Nisqually River, Threatened
Township:T16NR03E
Watershed Administrative Unit:Powell Creek
Watershed Administrative Unit:Tanwax Creek
WRIA:Nisqually
View project on a larger map
  APPLICATION FINAL 
ACQUISTION METRICS
Real Property Acquisition    
Miles of Streambank and/or Shoreline Protected by Land or Easement Acquisition
2.90mi2.90mi
 Land    
Acres by Acreage Type (fee simple)
Riparian
264.00
Total
264.00
acres
Riparian
79.00
Uplands
115.00
Wetlands
45.00
Total
239.00
acres
 
RESTORATION METRICS
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
0.02mi2.90mi
Fish Passage Improvement    
*Miles Of Stream Made Accessible (SRFB) (C.2.b.1)
3.00mi
*Number of blockages / impediments / barriers impeding passage (C.2.b.4)
3.00
Square Miles Of streambed made accessible (C.2.b.2)
0.05sq mi
 Fish passage blockages removed or altered (C.2.c.1)    
Change in water flow (fish passage project)(cu feet)
Number of Blockages/Impediments/Barriers Removed/Altered (C.2.c.2)
2.00
 Road-crossing removal (C.2.i.1)    
Miles of stream made accessible by road crossing removal (C.2.i.3)
3.00mi
Number of road-crossings (C.2.i.2)
1.00
Instream Habitat Project    
Total Miles Of Instream Habitat Treated (C.4.b)
0.00mi0.05mi
 Channel reconfiguration and connectivity (C.4.c.1)    
Acres Of Channel/Off-Channel Connected Or Added (C.4.c.5)
0.00acres
Instream Pools Created/Added (C.4.c.6)
0.00
Miles of Off-Channel Stream Created or Connected (C.4.c.4)
0.00mi
Miles of Stream Treated for channel reconfiguration and connectivity (C.4.c.3)
0.01mi
 Channel structure placement (C.4.d.1)    
Acres Of Streambed Treated for channel structure placement (C.4.d.4)
0.00acres
Miles of Stream Treated for channel structure placement (C.4.d.3)
0.00mi
Number of structures placed in channel (C.4.d.7)
1.00
Pools Created through channel structure placement (C.4.d.5)
0.00
Yards Of Average Stream-Width At Mid-Point Of Worksite (C.4.d.6)
0.00yd
 Streambank stabilization (C.4.e.1)    
Miles of Streambank Stabilized (C.4.e.3)
0.00mi0.00mi
Riparian Habitat Project    
*Total Riparian Acres Treated (C.5.b.2)
0.10acres
*Total Riparian Miles Streambank Treated (C.5.b.1)
0.00mi
 Planting (C.5.c.1)    
Acres Planted in riparian (C.5.c.3)
0.10acres
Upland Habitat And Sediment Project    
Acres of Upland Habitat Area Treated (C.6.b.1)
0.00acres
Miles of Road Treated (C.6.b.2)
0.01mi
 Road abandonment (C.6.d.1)    
Average width of road abandoned (in whole yards) (C.6.d.3)
0.00yd
Miles of Road Abandoned (C.6.d.2)
0.00mi
ADDITIONAL INFORMATION