Clear Creek Wetland and Floodplain Restoration
#13-1186 #13-1186
Organization West Sound Partners for Ecosystem Recovery
Sponsor Kitsap County Public Works
Status Dormant
Schedule Start Date: 8/25/2022 End Date: 8/25/2023
Category Category: Restoration
DESCRIPTION
Kitsap County Department of Public Works Surface and Stormwater Management (SSWM) Program is proposing a restoration project that will re-engage Clear Creek with its historical floodplain and restore 30 acres of floodplain, off-channel wetland, and riparian habitat within Clear Creek in Silverdale, WA.  Previous disturbances to the creek, floodplain, and riparian areas have resulted from retail and commercial developments, roads, and culverts, in addition to agricultural impacts such as ditching and channelization.  The project objectives include a) enhancing natural wetland and floodplain function by removing 3,100 feet of Schold Road NW to expand the stream channel across the floodplain, b) installing large woody debris to improve in-stream habitat and create complexity within the channel, c) removing 20 acres of invasive vegetation and d) replanting with native conifers and shrubs.  This project will improve salmon habitat and reduce the negative impacts of stormflows on coho, chum, steelhead, cutthroat and rainbow trout.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested08/09/2013Recreation and Conservation Office (RCO)Salmon State Projects$425,000.00
Requested08/09/2013Kitsap County Public WorksMatch$3,318,045.00
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$425,000.00 $3,743,045.00 $0.00 $0.00 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
ALT PROJECT CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Puget Sound, Threatened
Chum-Pop (ESU):Chum-Puget Sound/Strait of Georgia, Not Warranted
City Areas:Silverdale
Coho-Pop (ESU):Coho-Puget Sound/Strait of Georgia, Species of Concern
County:Kitsap
HUC12:Barker Creek-Frontal Dyes Inlet (171100190706)
HUC8:Puget Sound (17110019)
Lead Entity Area:West Sound
Legislative District:23
Pink-Pop (ESU):Pink-Odd Year, Not Warranted
Puget Sound Action Areas:North Central Puget Sound
Salmon Recovery Regions:Puget Sound
Sections:09
Steelhead-Pop (ESU):Steelhead-Puget Sound, East Kitsap Peninsula Tributaries, Threatened
Township:T25NR01E
Watershed Administrative Unit:Dyes Inlet
WRIA:Kitsap
View project on a larger map

Related Projects

  APPLICATION FINAL 
RESTORATION METRICS
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
0.38mi
Fish Passage Improvement    
*Miles Of Stream Made Accessible (SRFB) (C.2.b.1)
5.10mi
*Number of blockages / impediments / barriers impeding passage (C.2.b.4)
2.00
Square Miles Of streambed made accessible (C.2.b.2)
0.00sq mi
 Bridge installed or improved (C.2.g.1)    
Miles of stream made accessible by bridge installation/repair (C.2.g.3)
5.00mi
Number of bridges (C.2.g.2)
3.00
 Road-crossing removal (C.2.i.1)    
Miles of stream made accessible by road crossing removal (C.2.i.3)
5.09mi
Number of road-crossings (C.2.i.2)
2.00
Instream Habitat Project    
Total Miles Of Instream Habitat Treated (C.4.b)
0.30mi
 Channel reconfiguration and connectivity (C.4.c.1)    
Acres Of Channel/Off-Channel Connected Or Added (C.4.c.5)
0.10acres
Instream Pools Created/Added (C.4.c.6)
30.00
Miles of Off-Channel Stream Created or Connected (C.4.c.4)
0.10mi
Miles of Stream Treated for channel reconfiguration and connectivity (C.4.c.3)
0.38mi
 Channel structure placement (C.4.d.1)    
Acres Of Streambed Treated for channel structure placement (C.4.d.4)
0.00acres
Miles of Stream Treated for channel structure placement (C.4.d.3)
0.30mi
Number of structures placed in channel (C.4.d.7)
57.00
Pools Created through channel structure placement (C.4.d.5)
7.00
Yards Of Average Stream-Width At Mid-Point Of Worksite (C.4.d.6)
4.00yd
 Spawning gravel placement (C.4.f.1)    
Cubic Yards of spawning gravel placed (C.4.f.3)
484.00cubic yds
Miles of Stream Treated with spawning gravel placement (C.4.f.2)
0.08mi
Riparian Habitat Project    
*Total Riparian Acres Treated (C.5.b.2)
32.00acres
*Total Riparian Miles Streambank Treated (C.5.b.1)
0.30mi
 Planting (C.5.c.1)    
Acres Planted in riparian (C.5.c.3)
32.00acres
Miles of streambank planted (C.5.c.4)
0.45mi
 Riparian Plant removal / control (C.5.h.1)    
Acres of riparian treated for plant removal/control (C.5.h.3)
32.00acres
Miles of streambank treated for plant removal/control (C.5.h.4)
0.20mi