DESCRIPTION
All four projects will be conducted by Pierce Co, in cooperation with Peninsula Salmon and Pierce Co CD. Both projects involve replacing undersized or perched culverts at road crossings with appropriately sized, countersunk culverts or bridges. At each site, the fish-blocking culvert represents the limiting factor for salmon production by inhibiting adult and juvenile salmon migration for spawning and rearing. Minter Creek is one of two streams located in Pierce County west of the Narrows Bridge that is identified in the Washington State Stream Catalogue as a chinook bearing stream. The project would replace a private road crossing that consists of five separate small pipes with a small bridge. The result will be an additional 3.5 miles of stream accessible to salmon. Herron Ck is a private road crossing with a history of erosion, siltation and fish-blocking. This site is impacted by natural sediment and gravel movement through the stream that exceeds the culvert capacity. The culvert is also at the bottom of a steep-gradient unpaved road, which contributes additional sediment. The project removes two 36" concrete pipes with a single arched culvert to accommodate flows & the opening of 1.4 miles of habitat to salmon.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested03/19/1999Pierce Conservation DistrictMatch$44,690.00
Requested03/19/1999Recreation and Conservation Office (RCO)Salmon Federal Projects$68,310.00
Allocated01/27/2000Pierce Conservation DistrictMatch$52,229.93
Allocated01/27/2000Recreation and Conservation Office (RCO)Salmon Federal Projects$67,372.43
Spent01/26/2000Pierce Conservation DistrictMatch-$52,229.93
Spent01/26/2000Recreation and Conservation Office (RCO)Salmon Federal Projects-$67,372.43
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$118,665.00 $113,000.00 $119,602.36 $119,602.36 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
SECONDARY SPONSOR
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Puget Sound, Threatened
Chum-Pop (ESU):Chum-Puget Sound/Strait of Georgia, Not Warranted
City Areas:Longbranch
City Areas:Stansberry Lake
Coho-Pop (ESU):Coho-Puget Sound/Strait of Georgia, Species of Concern
County:Pierce
HUC12:Key Peninsula-Frontal Carr Inlet (171100190701)
HUC12:Key Peninsula-Frontal Case Inlet (171100190610)
HUC8:Puget Sound (17110019)
Lead Entity Area:West Sound
Legislative District:26
Pink-Pop (ESU):Pink-Odd Year, Not Warranted
Puget Sound Action Areas:South Puget Sound
Salmon Recovery Regions:Puget Sound
Sections:04
Sections:20
Steelhead-Pop (ESU):Steelhead-Puget Sound, South Puget Sound Tributaries, Threatened
Township:T20NR01W
Township:T22NR01E
Watershed Administrative Unit:Key Peninsula
WRIA:Kitsap
View project on a larger map
  APPLICATION FINAL 
RESTORATION METRICS
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
0.02mi0.02mi
Fish Passage Improvement    
*Miles Of Stream Made Accessible (SRFB) (C.2.b.1)
3.50mi7.00mi
*Number of blockages / impediments / barriers impeding passage (C.2.b.4)
3.00
Square Miles Of streambed made accessible (C.2.b.2)
 Bridge installed or improved (C.2.g.1)    
Miles of stream made accessible by bridge installation/repair (C.2.g.3)
3.50mi
Number of bridges (C.2.g.2)
1.00
 Culvert installed or improved (C.2.f.1)    
Miles of stream made accessible by culvert installation/repair (C.2.f.3)
3.50mi3.50mi
Number of culverts (C.2.f.2)
1.00
 Fish passage blockages removed or altered (C.2.c.1)    
Change in water flow (fish passage project)(cu feet)
Number of Blockages/Impediments/Barriers Removed/Altered (C.2.c.2)
2.002.00
 Road-crossing removal (C.2.i.1)    
Miles of stream made accessible by road crossing removal (C.2.i.3)
0.00mi0.00mi
Number of road-crossings (C.2.i.2)