East Fork Rocky Creek Bridge
#99-1446 #99-1446
 Case Inlet East Case Inlet, Key Peninsula East Fork Rocky Creek Bridge
Organization West Sound Partners for Ecosystem Recovery
Sponsor Pierce County Public Works and Utilities
Status Completed
Schedule Start Date: 7/29/1999 End Date: 3/16/2001
Category Category: Restoration
Project Photo
DESCRIPTION
The existing barrier consists of an 8' x 8' concrete box structure supporting the Wright-Bliss road. The box structure outlet elevation is about 4 feet above the outlet streambed. The structure size restricts normal flood water flow causing a backwater and flooding effect. Extreme velocities through the box structure result in downstream erosion. The proposed correction is to remove the box structure and replace it with a 61-foot long single span, pre-cast, pre-stressed concrete bridge.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested07/20/1999Pierce County Public Works and UtilitiesMatch$113,000.00
Requested07/20/1999Recreation and Conservation Office (RCO)Salmon State Projects$339,000.00
Allocated03/16/2001Pierce County Public Works and UtilitiesMatch$110,231.84
Allocated03/16/2001Recreation and Conservation Office (RCO)Salmon State Projects$330,695.50
Spent03/14/2001Pierce County Public Works and UtilitiesMatch-$110,231.84
Spent03/14/2001Recreation and Conservation Office (RCO)Salmon State Projects-$330,695.50
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$432,623.00 $452,000.00 $440,927.34 $440,927.34 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
SECONDARY SPONSOR
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Puget Sound, Threatened
Chum-Pop (ESU):Chum-Puget Sound/Strait of Georgia, Not Warranted
Coho-Pop (ESU):Coho-Puget Sound/Strait of Georgia, Species of Concern
County:Pierce
HUC12:Key Peninsula-Frontal Case Inlet (171100190610)
HUC8:Puget Sound (17110019)
Lead Entity Area:West Sound
Legislative District:26
Pink-Pop (ESU):Pink-Odd Year, Not Warranted
Puget Sound Action Areas:South Puget Sound
Salmon Recovery Regions:Puget Sound
Sections:23
Steelhead-Pop (ESU):Steelhead-Puget Sound, South Puget Sound Tributaries, Threatened
Township:T22NR01W
Watershed Administrative Unit:Key Peninsula
WRIA:Kitsap
View project on a larger map
  APPLICATION FINAL 
RESTORATION METRICS
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
0.10mi0.10mi
Fish Passage Improvement    
*Miles Of Stream Made Accessible (SRFB) (C.2.b.1)
4.00mi4.00mi
*Number of blockages / impediments / barriers impeding passage (C.2.b.4)
1.00
Square Miles Of streambed made accessible (C.2.b.2)
 Bridge installed or improved (C.2.g.1)    
Miles of stream made accessible by bridge installation/repair (C.2.g.3)
4.00mi
Number of bridges (C.2.g.2)
1.00
 Fish passage blockages removed or altered (C.2.c.1)    
Change in water flow (fish passage project)(cu feet)
Number of Blockages/Impediments/Barriers Removed/Altered (C.2.c.2)
1.001.00
 Fishway chutes or pools installed (C.2.d.1)    
Number Of Fishway Chutes/Pools Installed (C.2.d.2)
 Road-crossing removal (C.2.i.1)    
Miles of stream made accessible by road crossing removal (C.2.i.3)
0.00mi0.00mi
Number of road-crossings (C.2.i.2)