Keystone Preserve A&R - ESRP
#22-1157 #22-1157
Organization Island County Lead Entity
Sponsor Whidbey Camano Land Trust (WCLT)
Status Dormant
Schedule Start Date: 6/1/2022 End Date: 12/31/2023
Category Category: Acquisition & Restoration
DESCRIPTION
The Keystone Preserve Acquisition and Restoration project on Whidbey Island will protect 3,500 feet (2/3 mile) of Puget Sound shoreline including active and vegetated feeder bluffs, kelp and eelgrass beds that provide migratory habitat for Puget Sound salmon, including endangered Chinook. The project addresses the top priorities  of the WRIA 6 (Island) Multi-Species Salmon Recovery Plan - protection and restoration of natural marine shorelines and processes: Protection: The project will directly protect 3,500 feet of intact beach and tidelands on Admiralty Bay, along with 175 acres of the 226-acre Keystone Preserve property (the remaining 51-acres has been carved out ). The property is Geographic Area 3 of the WRIA 6 Multi-Species Salmon Recovery Plan, an area well known for large number of migrating salmon. Restoration: The project will also remove the existing beach house and ~300 feet of associated shoreline hard-armoring along the low-bank portion of the property. Hard-armor removal will be paid for by WDNR's Creosote Removal Program as project match. Under and enhanced project budget, coastal habitat buffers and riparian restoration can also take place, to revegetate 15-acres of open field along the shoreline to native plants, and restore and revegetate a stream.     
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested06/08/2022Recreation and Conservation Office (RCO)Estuary & Salmon Restoration$2,039,000.00
Requested06/08/2022Whidbey Camano Land Trust (WCLT)Match$7,412,000.00
Allocated07/01/2023Recreation and Conservation Office (RCO)Estuary & Salmon Restoration$2,039,000.00
Allocated07/01/2023Whidbey Camano Land Trust (WCLT)Match$7,412,000.00
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
Not entered $9,451,000.00 $9,451,000.00 $0.00 $9,451,000.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
ALT PROJECT CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Puget Sound, Threatened
Chum-Pop (ESU):Chum-Puget Sound/Strait of Georgia, Not Warranted
Coho-Pop (ESU):Coho-Puget Sound/Strait of Georgia, Species of Concern
County:Island
HUC12:Whidbey Island-Frontal Admiralty Inlet (171100190105)
HUC8:Puget Sound (17110019)
Lead Entity Area:Island County
Legislative District:10
Pink-Pop (ESU):Pink-Odd Year, Not Warranted
Puget Sound Action Areas:Whidbey Island
Salmon Recovery Regions:Puget Sound
Sections:19
Steelhead-Pop (ESU):Steelhead-Puget Sound, Threatened
Township:T31NR02E
Watershed Administrative Unit:Whidbey Island
WRIA:Island
View project on a larger map

Related Projects

  APPLICATION FINAL 
ACQUISTION METRICS
Incidentals    
 Noxious weed control    
Acres treated for noxious weeds by method
Chemical
50.00
Mechanical
15.00
Total
65.00
acres
Total
acres
Real Property Acquisition    
Miles of Streambank and/or Shoreline Protected by Land or Easement Acquisition
1.66mi
 Land    
Acres by Acreage Type (fee simple)
Lake
0.00
Riparian
35.60
Tidelands
3.80
Uplands
145.60
Wetlands
0.00
Total
185.00
acres
Total
acres
 
RESTORATION METRICS
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
1.25mi
Estuarine / Nearshore Project    
*Total Amount Of Estuarine / Nearshore Acres Treated (C.9.b)
2.00acres
 Shoreline armor removal or modification (C.9.k.1)    
Acres of Shoreline Treated for armor modification/removal (C.9.k.3)
2.00acres
Miles of Shoreline Treated for armor modification/removal (C.9.k.2)
0.06mi