Waterman Nearshore Acquisition
#06-NP-01-031 #06-NP-01-031
Organization Island County Lead Entity
Sponsor Whidbey Camano Land Trust (WCLT)
Status Completed
Schedule Start Date: 9/3/2014 End Date: 2/6/2017
Category Category: Acquisition
Project Photo
DESCRIPTION
This project includes the acquisition and permanent protection of 57 acres of nearshore and marine riparian habitat in Saratoga Pass. The project tract includes 31 acres of upland adjacent to 2000 ft of feeder bluff, 2 streams and 27 acres of tideland. The project will contribute to recovery of Puget Sound Chinook salmon and bull trout populations (ESA listed species). The property currently contains 434 ft of creosote hardshore armoring that will be removed.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested06/02/2014Whidbey Camano Land Trust (WCLT)Match$600,000.00
Requested06/02/2014Recreation and Conservation Office (RCO)Marine Shoreline Protection$600,000.00
Allocated11/02/2016Recreation and Conservation Office (RCO)Marine Shoreline Protection$98,875.97
Allocated11/02/2016Recreation and Conservation Office (RCO)Salmon State Projects$164,971.00
Allocated11/02/2016Recreation and Conservation Office (RCO)Puget Sound Acq. & Restoration$397,996.12
Allocated11/02/2016Whidbey Camano Land Trust (WCLT)Match$1,000,000.00
Spent08/13/2015Recreation and Conservation Office (RCO)Salmon State Projects-$164,971.00
Spent09/28/2015Recreation and Conservation Office (RCO)Puget Sound Acq. & Restoration-$397,996.12
Spent11/02/2016Recreation and Conservation Office (RCO)Marine Shoreline Protection-$98,875.97
Spent11/02/2016Whidbey Camano Land Trust (WCLT)Match-$1,000,000.00
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$2,163,000.00 $1,200,000.00 $1,661,843.09 $1,661,843.09 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Puget Sound, Threatened
Chum-Pop (ESU):Chum-Puget Sound/Strait of Georgia, Not Warranted
Coho-Pop (ESU):Coho-Puget Sound/Strait of Georgia, Species of Concern
County:Island
HUC12:Skagit Bay (171100191100)
HUC12:Whidbey Island-Frontal Possession Sound (171100190104)
HUC8:Puget Sound (17110019)
Lead Entity Area:Island County
Legislative District:10
Pink-Pop (ESU):Pink-Odd Year, Not Warranted
Puget Sound Action Areas:Whidbey Island
Salmon Recovery Regions:Puget Sound
Sections:13
Sections:14
Skagit Tiers:Tier 2 Pocket Estuaries
Steelhead-Pop (ESU):Steelhead-Puget Sound, Threatened
Township:T29NR03E
Watershed Administrative Unit:Whidbey Island
WRIA:Island
View project on a larger map
  APPLICATION FINAL 
ACQUISTION METRICS
Incidentals    
 Noxious weed control    
Acres treated for noxious weeds by method
Chemical
2.00
Mechanical
31.00
Total
33.00
acres
Chemical
2.00
Mechanical
31.00
Total
33.00
acres
Real Property Acquisition    
Miles of Streambank and/or Shoreline Protected by Land or Easement Acquisition
0.92mi0.92mi
 Land    
Acres by Acreage Type (fee simple)
Tidelands
26.00
Uplands
26.94
Wetlands
6.00
Total
58.94
acres
Tidelands
26.00
Uplands
26.94
Wetlands
6.00
Total
58.94
acres
 
WORKSITE METRICS
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
0.92mi