Dungeness R. Floodplain Restoration-Robinson Phase
#15-1055 #15-1055
 WRIA18 East: Dungeness River Watershed Dungeness River Mainstem Dungeness R. Floodplain Restoration-Robinson Phase
Organization North Olympic Peninsula Lead Entity for Salmon
Sponsor Jamestown S'Klallam Tribe
Status Completed
Schedule Start Date: 10/15/2015 End Date: 10/23/2019
Category Category: Acquisition & Restoration
DESCRIPTION
The Tribe acquired the several properties. The project included purchasing up to 29 acres of floodplain habitat, which was exceeded. A total of 32.33 acres were purchased. A total of 9 development rights along the Dungeness river were extinguished, and three residents utilized relocation assistance funds. Demolition of structures and decommissioning of utilities (on-site septic system, wells, PUD power, landline phone service) of purchased parcels, happened on the Robinson, Flath & Craft, and Smith LLC properties. A volunteer planting day on the Robinson properties occurred in January of 2018. The Tribe is working on a draft conservation stewardship plan, and when completed the plan will be used to provide guidance to Tribal leaders, Staff, and Tribal Citizens on management of lands purchased for conservation purposes.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested08/12/2015Jamestown S'Klallam TribeMatch$204,300.00
Requested08/12/2015Recreation and Conservation Office (RCO)Salmon State Projects$1,157,700.00
Allocated10/18/2019Jamestown S'Klallam TribeMatch$206,792.34
Allocated10/18/2019Recreation and Conservation Office (RCO)Puget Sound Acq. & Restoration$1,146,266.57
Spent10/18/2019Jamestown S'Klallam TribeMatch-$206,792.34
Spent10/18/2019Recreation and Conservation Office (RCO)Puget Sound Acq. & Restoration-$1,146,266.57
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$1,362,000.00 $1,362,000.00 $1,353,058.91 $1,353,058.91 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
ALT PROJECT CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Puget Sound, Dungeness River, Threatened
Chum-Pop (ESU):Chum-Hood Canal, Strait of Juan de Fuca, Threatened
Coho-Pop (ESU):Coho-Puget Sound/Strait of Georgia, Species of Concern
County:Clallam
HUC12:Lower Dungeness River (171100200307)
HUC12:Middle Dungeness River (171100200306)
HUC8:Dungeness-Elwha (17110020)
Lead Entity Area:North Olympic Peninsula
Legislative District:24
Pink-Pop (ESU):Pink-Odd Year, Not Warranted
Puget Sound Action Areas:Strait of Juan de Fuca
Salmon Recovery Regions:Hood Canal
Sections:01
Sections:02
Sections:23
Sections:26
Sections:35
Sections:36
Steelhead-Pop (ESU):Steelhead-Puget Sound, Dungeness River, Threatened
Township:T29NR04W
Township:T30NR04W
Watershed Administrative Unit:Dungeness Valley
WRIA:Elwha - Dungeness
View project on a larger map
  APPLICATION FINAL 
ACQUISTION METRICS
Incidentals    
 Noxious weed control    
Acres treated for noxious weeds by method
Mechanical
3.00
Total
3.00
acres
Mechanical
3.00
Total
3.00
acres
Real Property Acquisition    
Miles of Streambank and/or Shoreline Protected by Land or Easement Acquisition
0.75mi0.93mi
 Land    
Acres by Acreage Type (fee simple)
Lake
0.00
Riparian
27.52
Tidelands
0.00
Uplands
0.00
Wetlands
0.00
Total
27.52
acres
Riparian
32.46
Total
32.46
acres
 
RESTORATION METRICS
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
0.56mi0.56mi
Riparian Habitat Project    
*Total Riparian Acres Treated (C.5.b.2)
1.00acres1.00acres
*Total Riparian Miles Streambank Treated (C.5.b.1)
0.29mi0.29mi
 Debris/structures removal (C.5.j.1)    
Acres of Riparian Area Treated. (C.5.j.2)
1.00acres