Organization | North Olympic Peninsula Lead Entity for Salmon |
Sponsor | Department of Natural Resources (DNR) |
Status | Completed |
Schedule | Start Date: 2/15/2005 End Date: 1/31/2006 |
Category | Category: Restoration |
Type | Date | Funding Org | Funding Program | Match | Amount |
---|---|---|---|---|---|
Requested | 07/07/2004 | Department of Natural Resources (DNR) | Match | $44,426.00 | |
Requested | 07/07/2004 | Recreation and Conservation Office (RCO) | Salmon State Projects | $248,407.00 | |
Allocated | 01/06/2005 | Department of Natural Resources (DNR) | Match | $44,426.00 | |
Allocated | 01/06/2005 | Recreation and Conservation Office (RCO) | Salmon Federal Projects | $248,407.00 | |
Spent | 01/31/2006 | Department of Natural Resources (DNR) | Match | -$44,426.00 | |
Spent | 01/31/2006 | Recreation and Conservation Office (RCO) | Salmon Federal Projects | -$248,407.00 |
Grant Project Agreement Totals | Proposed | Requested | Allocated | Spent | Balance |
$292,833.00 | $292,833.00 | $292,833.00 | $292,833.00 | $0.00 |
Type | Date | Funding Org | Funding Program | Match | Amount |
---|
Other Funding Totals | Proposed | Requested | Allocated | Spent | Balance |
Grand Totals | Proposed | Requested | Allocated | Spent | Balance |
Chinook-Pop (ESU): | Chinook-Washington Coast, Not Warranted |
Chum-Pop (ESU): | Chum-Pacific Coast, Not Warranted |
Coho-Pop (ESU): | Coho-Olympic Peninsula, Not Warranted |
County: | Clallam |
HUC12: | East Twin River (171100210302) |
HUC12: | Susie Creek-Lyre River (171100210203) |
HUC8: | Crescent-Hoko (17110021) |
Lead Entity Area: | North Olympic Peninsula |
Legislative District: | 24 |
Puget Sound Action Areas: | Strait of Juan de Fuca |
Salmon Recovery Regions: | Puget Sound |
Sections: | 05 |
Sections: | 06 |
Steelhead-Pop (ESU): | Steelhead-Olympic Peninsula, Not Warranted |
Township: | T30NR09W |
Watershed Administrative Unit: | Lake Crescent |
Watershed Administrative Unit: | Twin Rivers-Deep Creek |
WRIA: | Lyre - Hoko |
APPLICATION | FINAL | ||||
RESTORATION METRICS | |||||
Miles of Stream and/or Shoreline Treated or Protected (C.0.b) | 0.20 | mi | 1.31 | mi | |
Fish Passage Improvement | |||||
*Miles Of Stream Made Accessible (SRFB) (C.2.b.1) | 1.10 | mi | 1.31 | mi | |
*Number of blockages / impediments / barriers impeding passage (C.2.b.4) | 5.00 | ||||
Square Miles Of streambed made accessible (C.2.b.2) | 0.00 | sq mi | |||
Bridge installed or improved (C.2.g.1) | |||||
Miles of stream made accessible by bridge installation/repair (C.2.g.3) | 0.80 | mi | |||
Number of bridges (C.2.g.2) | 2.00 | ||||
Culvert installed or improved (C.2.f.1) | |||||
Miles of stream made accessible by culvert installation/repair (C.2.f.3) | 1.41 | mi | |||
Number of culverts (C.2.f.2) | 3.00 | ||||
Fish passage blockages removed or altered (C.2.c.1) | |||||
Change in water flow (fish passage project)(cu feet) | 0.00 | cfs | |||
Number of Blockages/Impediments/Barriers Removed/Altered (C.2.c.2) | 5.00 | 5.00 | |||
Instream Habitat Project | |||||
Total Miles Of Instream Habitat Treated (C.4.b) | 0.15 | mi | |||
Channel structure placement (C.4.d.1) | |||||
Acres Of Streambed Treated for channel structure placement (C.4.d.4) | 0.00 | acres | |||
Miles of Stream Treated for channel structure placement (C.4.d.3) | 0.15 | mi | |||
Number of structures placed in channel (C.4.d.7) | 20.00 | ||||
Pools Created through channel structure placement (C.4.d.5) | 18.00 | ||||
Yards Of Average Stream-Width At Mid-Point Of Worksite (C.4.d.6) | 0.00 | yd |