Organization | Hood Canal Coordinating Council Lead Entity |
Sponsor | Northwest Watershed Institute |
Status | Completed |
Schedule | Start Date: 8/1/2015 End Date: 5/25/2018 |
Category | Category: Acquisition & Restoration |
Type | Date | Funding Org | Funding Program | Match | Amount |
---|---|---|---|---|---|
Requested | 09/12/2014 | Northwest Watershed Institute | Match | $300,000.00 | |
Requested | 09/12/2014 | Recreation and Conservation Office (RCO) | Estuary & Salmon Restoration | $527,000.00 | |
Allocated | 05/23/2018 | Northwest Watershed Institute | Match | $300,000.00 | |
Allocated | 05/23/2018 | Recreation and Conservation Office (RCO) | Estuary & Salmon Restoration | $536,966.72 | |
Spent | 05/23/2018 | Northwest Watershed Institute | Match | -$300,000.00 | |
Spent | 05/23/2018 | Recreation and Conservation Office (RCO) | Estuary & Salmon Restoration | -$536,966.72 |
Grant Project Agreement Totals | Proposed | Requested | Allocated | Spent | Balance |
$827,000.00 | $827,000.00 | $836,966.72 | $836,966.72 | $0.00 |
Type | Date | Funding Org | Funding Program | Match | Amount |
---|
Other Funding Totals | Proposed | Requested | Allocated | Spent | Balance |
Grand Totals | Proposed | Requested | Allocated | Spent | Balance |
Chinook-Pop (ESU): | Chinook-Puget Sound, Threatened |
Chum-Pop (ESU): | Chum-Hood Canal, Hood Canal, Threatened |
Chum-Pop (ESU): | Chum-Puget Sound/Strait of Georgia, Not Warranted |
Coho-Pop (ESU): | Coho-Puget Sound/Strait of Georgia, Species of Concern |
County: | Jefferson |
HUC12: | Hood Canal (171100180800) |
HUC12: | Tarboo Creek-Frontal Dabob Bay (171100180703) |
HUC8: | Hood Canal (17110018) |
Lead Entity Area: | Hood Canal |
Legislative District: | 24 |
Pink-Pop (ESU): | Pink-Odd Year, Not Warranted |
Puget Sound Action Areas: | Hood Canal |
Salmon Recovery Regions: | Hood Canal |
Sections: | 17 |
Sections: | 22 |
Steelhead-Pop (ESU): | Steelhead-Puget Sound, Threatened |
Steelhead-Pop (ESU): | Steelhead-Puget Sound, West Hood Canal Tributaries, Threatened |
Township: | T27NR01W |
Watershed Administrative Unit: | Toandos Peninsula |
WRIA: | Quilcene - Snow |
APPLICATION | FINAL | ||||
ACQUISTION METRICS | |||||
Real Property Acquisition | |||||
Miles of Streambank and/or Shoreline Protected by Land or Easement Acquisition | 0.18 | mi | 0.18 | mi | |
Land | |||||
Acres by Acreage Type (fee simple) | Lake 0.00 Riparian 7.00 Tidelands 2.00 Uplands 0.00 Wetlands 0.00 Total 9.00 | acres | Lake 0.00 Riparian 7.00 Tidelands 2.00 Uplands 0.00 Total 9.00 | acres | |
RESTORATION METRICS | |||||
Miles of Stream and/or Shoreline Treated or Protected (C.0.b) | 0.20 | mi | 0.20 | mi | |
Estuarine / Nearshore Project | |||||
*Total Amount Of Estuarine / Nearshore Acres Treated (C.9.b) | 2.00 | acres | 2.00 | acres | |
Regrading of slope (C.9.i.1) | |||||
Acres of Estuary Treated through slope regrading (C.9.i.2) | 3.00 | acres | 3.00 | acres | |
Removal of existing fill material (C.9.g.1) | |||||
Acres of Estuary Treated through fill material removal (C.9.g.2) | 0.20 | acres | 0.20 | acres | |
Shoreline armor removal or modification (C.9.k.1) | |||||
Acres of Shoreline Treated for armor modification/removal (C.9.k.3) | 3.00 | acres | 3.00 | acres | |
Miles of Shoreline Treated for armor modification/removal (C.9.k.2) | 0.08 | mi | 0.08 | mi | |
Fish Passage Improvement | |||||
*Miles Of Stream Made Accessible (SRFB) (C.2.b.1) | 2.00 | mi | 2.00 | mi | |
*Number of blockages / impediments / barriers impeding passage (C.2.b.4) | 1.00 | 1.00 | |||
Square Miles Of streambed made accessible (C.2.b.2) | 0.10 | sq mi | 0.10 | sq mi | |
Road-crossing removal (C.2.i.1) | |||||
Miles of stream made accessible by road crossing removal (C.2.i.3) | 2.00 | mi | 2.00 | mi | |
Number of road-crossings (C.2.i.2) | 1.00 | 1.00 | |||
Instream Habitat Project | |||||
Total Miles Of Instream Habitat Treated (C.4.b) | 0.20 | mi | 0.20 | mi | |
Channel reconfiguration and connectivity (C.4.c.1) | |||||
Acres Of Channel/Off-Channel Connected Or Added (C.4.c.5) | 0.10 | acres | 0.10 | acres | |
Instream Pools Created/Added (C.4.c.6) | 50.00 | 50.00 | |||
Miles of Off-Channel Stream Created or Connected (C.4.c.4) | 0.01 | mi | 0.01 | mi | |
Miles of Stream Treated for channel reconfiguration and connectivity (C.4.c.3) | 0.20 | mi | 0.20 | mi | |
Channel structure placement (C.4.d.1) | |||||
Acres Of Streambed Treated for channel structure placement (C.4.d.4) | 0.20 | acres | 0.20 | acres | |
Miles of Stream Treated for channel structure placement (C.4.d.3) | 0.20 | mi | 0.20 | mi | |
Number of structures placed in channel (C.4.d.7) | 150.00 | 150.00 | |||
Pools Created through channel structure placement (C.4.d.5) | 50.00 | 50.00 | |||
Yards Of Average Stream-Width At Mid-Point Of Worksite (C.4.d.6) | 2.00 | yd | 2.00 | yd | |
Spawning gravel placement (C.4.f.1) | |||||
Cubic Yards of spawning gravel placed (C.4.f.3) | 150.00 | cubic yds | 150.00 | cubic yds | |
Miles of Stream Treated with spawning gravel placement (C.4.f.2) | 0.20 | mi | 0.20 | mi | |
Riparian Habitat Project | |||||
*Total Riparian Acres Treated (C.5.b.2) | 6.00 | acres | 6.00 | acres | |
*Total Riparian Miles Streambank Treated (C.5.b.1) | 0.40 | mi | 0.40 | mi | |
Planting (C.5.c.1) | |||||
Acres Planted in riparian (C.5.c.3) | 6.00 | acres | 6.00 | acres | |
Miles of streambank planted (C.5.c.4) | 0.20 | mi | 0.20 | mi | |
Riparian Plant removal / control (C.5.h.1) | |||||
Acres of riparian treated for plant removal/control (C.5.h.3) | 6.00 | acres | 6.00 | acres | |
Miles of streambank treated for plant removal/control (C.5.h.4) | 0.20 | mi | 0.20 | mi |