Fort Townsend State Park Shoreline Restoration
#07-02-14577 #07-02-14577
 Jefferson County- Nearshore Jefferson County Nearshore Restoration Fort Townsend State Park Shoreline Restoration
Organization Hood Canal Coordinating Council Lead Entity
Sponsor Northwest Straits Marine Conservation Foundation
Status Completed
Schedule Start Date: 7/1/2013 End Date: 1/25/2017
Category Category: Restoration
Project Photo
DESCRIPTION
The Northwest Straits Foundation is partnering with the Jefferson County Marine Resources Committee, and Washington State Parks to conduct feasibility assessment, final design, permitting and implementation for the removal of roughly 1400 cubic yards of fill and large rip rap from a bluff-backed beach and adjacent intertidal area This project will restore of approximately 9000 square feet of nearshore habitat benefitting salmonids and forage fish and waterfowl at Fort Townsend State Park in Jefferson County. The project area is a filled and armored landing, backed by a feeder bluff, used by park visitors to picnic and launch kayaks.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested05/22/2013Northwest Straits Marine Conservation FoundationMatch$17,242.00
Requested05/22/2013Recreation and Conservation Office (RCO)Estuary & Salmon Restoration$52,126.00
Allocated01/25/2017Northwest Straits Marine Conservation FoundationMatch$15,825.79
Allocated01/25/2017Recreation and Conservation Office (RCO)ESRP-EPA Marine & Nearshore$480,249.71
Spent11/23/2016Recreation and Conservation Office (RCO)Salmon State Projects-$0.00
Spent01/25/2017Northwest Straits Marine Conservation FoundationMatch-$15,825.79
Spent01/25/2017Recreation and Conservation Office (RCO)ESRP-EPA Marine & Nearshore-$480,249.71
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$532,405.71 $69,368.00 $496,075.50 $496,075.50 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
SECONDARY SPONSOR
ALT PROJECT CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Puget Sound, Threatened
Chum-Pop (ESU):Chum-Hood Canal, Strait of Juan de Fuca, Threatened
Chum-Pop (ESU):Chum-Puget Sound/Strait of Georgia, Not Warranted
Coho-Pop (ESU):Coho-Puget Sound/Strait of Georgia, Species of Concern
County:Jefferson
HUC12:Marrowstone Island-Frontal Port Townsend (171100190803)
HUC12:Puget Sound (171100191200)
HUC8:Puget Sound (17110019)
Lead Entity Area:Hood Canal
Legislative District:24
Pink-Pop (ESU):Pink-Odd Year, Not Warranted
Puget Sound Action Areas:Hood Canal
Salmon Recovery Regions:Hood Canal
Sections:22
Steelhead-Pop (ESU):Steelhead-Puget Sound, Sequim/Discovery Bays Tributaries, Threatened
Steelhead-Pop (ESU):Steelhead-Puget Sound, Threatened
Township:T30NR01W
Watershed Administrative Unit:Chimakum
WRIA:Quilcene - Snow
View project on a larger map
  APPLICATION FINAL 
RESTORATION METRICS
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
0.00mi
Estuarine / Nearshore Project    
*Total Amount Of Estuarine / Nearshore Acres Treated (C.9.b)
0.20acres
 Estuarine planting or native plant establishment (C.9.r.1)    
Acres of Estuarine planting or native plant establishment (C.9.r.3)
0.10acres
 Regrading of slope (C.9.i.1)    
Acres of Estuary Treated through slope regrading (C.9.i.2)
0.20acres
 Shoreline armor removal or modification (C.9.k.1)    
Acres of Shoreline Treated for armor modification/removal (C.9.k.3)
0.10acres
Miles of Shoreline Treated for armor modification/removal (C.9.k.2)
0.20mi