Bear Creek Fish Barrier Removal
#11-04-14179 #11-04-14179
 Mason County- Union Union Fish Passage Bear Creek Fish Barrier Removal
Organization Hood Canal Coordinating Council Lead Entity
Sponsor Mason County Public Works
Status Completed
Schedule Start Date: 1/1/1999 End Date: 11/20/2001
Category Category: Restoration
DESCRIPTION
Bear Creek is a tributary to the Union River, which has a low but stable population of summer chum. The culvert under Old Navy Yard Way poses upstream migration problems near the mouth of Bear Creek. The existing culvert is a 71"x 47" culvert with a pipe capacity of 140 cfs at velocities of >15 fps. The culvert has a 30" perch with rock and concrete rubble blocking a 3' plunge pool at the downstream end. The average stream width above and below the culvert is 11 feet with a 100 year flood flow of 300 cfs. The culvert is undersized, is a velocity barrier during high flows and is inaccessible to chum due to the perch at the downstream end. The salmon bang away at this culvert for days and can not get through. It is pathetic to watch. Replacing this culvert would open up approximately 0.75 miles of chum habitat and a total of 3.75 miles of good habitat for other salmonids, such as coho and steelhead. In addition, 3 acres of prime wetland habitat can be utilized by overwintering coho. Local citizens groups are working to rebuild the declining numbers of chinook in the system. This project can be accomplished during the hydraulic code work window, summer/fall 1999.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested03/14/1999Recreation and Conservation Office (RCO)Salmon Federal Projects$90,000.00
Allocated06/03/1999Recreation and Conservation Office (RCO)Salmon Federal Projects$90,000.00
Spent11/08/2000Mason County Public WorksMatch-$0.00
Spent11/08/2000Recreation and Conservation Office (RCO)Salmon Federal Projects-$90,000.00
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$90,000.00 $90,000.00 $90,000.00 $90,000.00 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Puget Sound, Threatened
Chum-Pop (ESU):Chum-Hood Canal, Hood Canal, Threatened
City Areas:Belfair
Coho-Pop (ESU):Coho-Puget Sound/Strait of Georgia, Species of Concern
County:Mason
HUC12:Union River (171100180101)
HUC8:Hood Canal (17110018)
Lead Entity Area:Hood Canal
Legislative District:35
Pink-Pop (ESU):Pink-Odd Year, Not Warranted
Puget Sound Action Areas:Hood Canal
Salmon Recovery Regions:Hood Canal
Sections:09
Sections:29
Steelhead-Pop (ESU):Steelhead-Puget Sound, South Hood Canal Tributaries, Threatened
Township:T23NR01W
Watershed Administrative Unit:Lynch Cove
WRIA:Kitsap
View project on a larger map
  APPLICATION FINAL 
RESTORATION METRICS
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
0.01mi0.01mi
Fish Passage Improvement    
*Miles Of Stream Made Accessible (SRFB) (C.2.b.1)
4.00mi4.00mi
*Number of blockages / impediments / barriers impeding passage (C.2.b.4)
1.00
Square Miles Of streambed made accessible (C.2.b.2)
 Culvert installed or improved (C.2.f.1)    
Miles of stream made accessible by culvert installation/repair (C.2.f.3)
4.00mi4.00mi
Number of culverts (C.2.f.2)
 Fish passage blockages removed or altered (C.2.c.1)    
Change in water flow (fish passage project)(cu feet)
Number of Blockages/Impediments/Barriers Removed/Altered (C.2.c.2)
1.001.00
 Road-crossing removal (C.2.i.1)    
Miles of stream made accessible by road crossing removal (C.2.i.3)
0.00mi0.00mi
Number of road-crossings (C.2.i.2)