Organization | Hood Canal Coordinating Council Lead Entity |
Sponsor | Mason County Public Works |
Status | Completed |
Schedule | Start Date: 4/16/1999 End Date: 11/20/2001 |
Category | Category: Restoration |
Type | Date | Funding Org | Funding Program | Match | Amount |
---|---|---|---|---|---|
Requested | 02/01/1999 | Mason County Public Works | Match | $15,000.00 | |
Requested | 02/01/1999 | Recreation and Conservation Office (RCO) | Salmon Federal Projects | $52,969.00 | |
Allocated | 05/13/1999 | Mason County Public Works | Match | $15,000.00 | |
Allocated | 05/13/1999 | Recreation and Conservation Office (RCO) | Salmon Federal Projects | $52,969.00 | |
Spent | 11/08/2000 | Mason County Public Works | Match | -$15,000.00 | |
Spent | 11/08/2000 | Recreation and Conservation Office (RCO) | Salmon Federal Projects | -$52,969.00 |
Grant Project Agreement Totals | Proposed | Requested | Allocated | Spent | Balance |
$67,969.00 | $67,969.00 | $67,969.00 | $67,969.00 | $0.00 |
Type | Date | Funding Org | Funding Program | Match | Amount |
---|
Other Funding Totals | Proposed | Requested | Allocated | Spent | Balance |
Grand Totals | Proposed | Requested | Allocated | Spent | Balance |
Chinook-Pop (ESU): | Chinook-Puget Sound, Threatened |
Chum-Pop (ESU): | Chum-Hood Canal, Hood Canal, Threatened |
Coho-Pop (ESU): | Coho-Puget Sound/Strait of Georgia, Species of Concern |
County: | Mason |
HUC12: | Tahuya River (171100180104) |
HUC8: | Hood Canal (17110018) |
Lead Entity Area: | Hood Canal |
Legislative District: | 35 |
Pink-Pop (ESU): | Pink-Odd Year, Not Warranted |
Puget Sound Action Areas: | Hood Canal |
Salmon Recovery Regions: | Hood Canal |
Sections: | 22 |
Steelhead-Pop (ESU): | Steelhead-Puget Sound, South Hood Canal Tributaries, Threatened |
Township: | T22NR03W |
Watershed Administrative Unit: | Great Bend |
WRIA: | Kitsap |
APPLICATION | FINAL | ||||
RESTORATION METRICS | |||||
Miles of Stream and/or Shoreline Treated or Protected (C.0.b) | 0.01 | mi | 0.01 | mi | |
Fish Passage Improvement | |||||
*Miles Of Stream Made Accessible (SRFB) (C.2.b.1) | 8.00 | mi | 8.00 | mi | |
*Number of blockages / impediments / barriers impeding passage (C.2.b.4) | 1.00 | ||||
Square Miles Of streambed made accessible (C.2.b.2) | |||||
Culvert installed or improved (C.2.f.1) | |||||
Miles of stream made accessible by culvert installation/repair (C.2.f.3) | 8.00 | mi | 8.00 | mi | |
Number of culverts (C.2.f.2) | |||||
Fish passage blockages removed or altered (C.2.c.1) | |||||
Change in water flow (fish passage project)(cu feet) | |||||
Number of Blockages/Impediments/Barriers Removed/Altered (C.2.c.2) | 1.00 | 1.00 | |||
Road-crossing removal (C.2.i.1) | |||||
Miles of stream made accessible by road crossing removal (C.2.i.3) | 0.00 | mi | 0.00 | mi | |
Number of road-crossings (C.2.i.2) |