Hamma Hamma River Estuary Restoration
#08-03-12976 #08-03-12976
Organization Hood Canal Coordinating Council Lead Entity
Sponsor Hood Canal Salmon Enhancement Group (HCSEG)
Status Completed
Schedule Start Date: 2/1/2007 End Date: 10/7/2011
Category Category: Restoration
Project Photo
DESCRIPTION
This project was originally started as Recreation and Conservation Office's Project Information System (PRISM) project # 09-1677.  However, the two PRISM projects and their funding were combined to implement the project described above, with details outlined in #06-2221 under a new project agreement.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested09/15/2006Hood Canal Salmon Enhancement Group (HCSEG)Match$32,686.00
Requested09/15/2006Recreation and Conservation Office (RCO)Salmon State Projects$81,799.00
Allocated01/03/2011Hood Canal Salmon Enhancement Group (HCSEG)Match$85,340.49
Allocated01/03/2011Recreation and Conservation Office (RCO)Salmon State Projects$204,466.56
Spent10/07/2011Hood Canal Salmon Enhancement Group (HCSEG)Match-$85,340.49
Spent10/07/2011Recreation and Conservation Office (RCO)Salmon State Projects-$204,466.56
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$289,807.00 $114,485.00 $289,807.05 $289,807.05 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Puget Sound, Threatened
Chum-Pop (ESU):Chum-Hood Canal, Hood Canal, Threatened
Chum-Pop (ESU):Chum-Puget Sound/Strait of Georgia, Not Warranted
Coho-Pop (ESU):Coho-Puget Sound/Strait of Georgia, Species of Concern
County:Mason
HUC12:Eagle Creek-Frontal Hood Canal (171100180303)
HUC12:Hood Canal (171100180800)
HUC8:Hood Canal (17110018)
Lead Entity Area:Hood Canal
Legislative District:35
Pink-Pop (ESU):Pink-Odd Year, Not Warranted
Puget Sound Action Areas:Hood Canal
Salmon Recovery Regions:Hood Canal
Sections:26
Sections:27
Steelhead-Pop (ESU):Steelhead-Puget Sound, Threatened
Steelhead-Pop (ESU):Steelhead-Puget Sound, West Hood Canal Tributaries, Threatened
Township:T24NR03W
Watershed Administrative Unit:Hamma Hamma
WRIA:Skokomish - Dosewallips
View project on a larger map
  APPLICATION FINAL 
RESTORATION METRICS
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
0.00mi0.00mi
Estuarine / Nearshore Project    
*Total Amount Of Estuarine / Nearshore Acres Treated (C.9.b)
0.20acres0.20acres
 Beach nourishment (C.9.l.1)    
Acres Treated for beach nourishment (C.9.l.4)
0.20acres
Cubic Yards Of Beach Substrate Placed (C.9.l.2)
20.00cubic yds
Miles of Shoreline Treated for beach nourishment (C.9.l.3)
0.03mi
 Creation of new estuarine area (C.9.q.1)    
Acres of Estuary Created (C.9.q.2)
0.00acres1.80acres
 Debris removal (C.9.n.1)    
Acres Treated for debris removal (C.9.n.2)
0.10acres
 Estuarine plant removal / control (C.9.j.1)    
Acres of Estuary Treated for plant removal/control (C.9.j.3)
0.00acres0.00acres
 Regrading of slope (C.9.i.1)    
Acres of Estuary Treated through slope regrading (C.9.i.2)
0.20acres
 Shoreline armor removal or modification (C.9.k.1)    
Acres of Shoreline Treated for armor modification/removal (C.9.k.3)
0.00acres
Miles of Shoreline Treated for armor modification/removal (C.9.k.2)
0.00mi
 Tidegate alteration / removal (C.9.e.1)    
Acres opened To Fish Passage through tidegate alteration/removal (C.9.e.3)
0.00acres
Miles of stream made accessible by removal or modification of tidegate
Number of Tidegates Altered/Removed To Allow Fish Passage (C.9.e.2)
0.00
Fish Passage Improvement    
*Miles Of Stream Made Accessible (SRFB) (C.2.b.1)
0.00mi0.00mi
*Number of blockages / impediments / barriers impeding passage (C.2.b.4)
0.00
Square Miles Of streambed made accessible (C.2.b.2)
0.00sq mi
 Fish passage blockages removed or altered (C.2.c.1)    
Change in water flow (fish passage project)(cu feet)
0.00cfs
Number of Blockages/Impediments/Barriers Removed/Altered (C.2.c.2)
1.000.00
 Road-crossing removal (C.2.i.1)    
Miles of stream made accessible by road crossing removal (C.2.i.3)
0.00mi0.00mi
Number of road-crossings (C.2.i.2)
0.00
Instream Habitat Project    
Total Miles Of Instream Habitat Treated (C.4.b)
0.10mi0.11mi
 Channel reconfiguration and connectivity (C.4.c.1)    
Acres Of Channel/Off-Channel Connected Or Added (C.4.c.5)
Instream Pools Created/Added (C.4.c.6)
Miles of Off-Channel Stream Created or Connected (C.4.c.4)
Miles of Stream Treated for channel reconfiguration and connectivity (C.4.c.3)
0.04mi
 Channel structure placement (C.4.d.1)    
Miles of Stream Treated for channel structure placement (C.4.d.3)
0.11mi
Number of structures placed in channel (C.4.d.7)
7.00
Pools Created through channel structure placement (C.4.d.5)
 Streambank stabilization (C.4.e.1)    
Miles of Streambank Stabilized (C.4.e.3)
0.00mi0.05mi
Real Property Acquisition    
 Acquisition or lease of land, wetland or estuarine for conservation (C.10.c.1)    
Miles Of Streambank Protected By Land or Easement Acquisition (C.10.c.5)