Organization | Kennedy-Goldsborough Basin (WRIA 14) Salmon Recovery Lead Entity |
Sponsor | South Puget Sound Salmon Enhancement Group (SPSSEG) |
Status | Active |
Schedule | Start Date: 9/23/2021 End Date: 5/1/2027 |
Category | Category: Restoration |
The proposed project will complete Phase 2C (North salt marsh lobe) of the larger West Oakland Bay Conservation and Restoration project. Phases 1 (LWD construction) and 4 (Eagle Point conservation) and 2B (North saltmarsh lobe) have been completed. Phase 2C (South salt marsh lobe) is under construction. The funding of Phase 2C will complete the project.
Restoration components include the removal of 1/4 mile of bulkhead and the enhancement of 17 acres of saltmarsh to promote the growth of intertidal vegetation. All restoration will occur in areas rated as High Priority and Enhance High Priority. Designs are complete and all permits are in place.
Type | Date | Funding Org | Funding Program | Match | Amount |
---|---|---|---|---|---|
Requested | 02/26/2020 | South Puget Sound Salmon Enhancement Group (SPSSEG) | Match | $1,013,652.00 | |
Requested | 02/26/2020 | Recreation and Conservation Office (RCO) | PSAR Large Capital Projects | $5,730,376.00 | |
Allocated | 11/01/2023 | Recreation and Conservation Office (RCO) | Salmon State Projects | $120,245.00 | |
Allocated | 11/01/2023 | Recreation and Conservation Office (RCO) | Puget Sound Acq. & Restoration | $333,334.00 | |
Allocated | 11/01/2023 | South Puget Sound Salmon Enhancement Group (SPSSEG) | Match | $712,352.00 | |
Allocated | 11/01/2023 | Recreation and Conservation Office (RCO) | PSAR Large Capital Projects | $5,310,000.00 | |
Spent | 05/01/2025 | South Puget Sound Salmon Enhancement Group (SPSSEG) | Match | -$29,349.47 | |
Spent | 05/01/2025 | Recreation and Conservation Office (RCO) | Puget Sound Acq. & Restoration | -$237,464.06 |
Grant Project Agreement Totals | Proposed | Requested | Allocated | Spent | Balance |
$7,077,362.00 | $6,744,028.00 | $6,475,931.00 | $266,813.53 | $6,209,117.47 |
Type | Date | Funding Org | Funding Program | Match | Amount |
---|
Other Funding Totals | Proposed | Requested | Allocated | Spent | Balance |
Grand Totals | Proposed | Requested | Allocated | Spent | Balance |
Chinook-Pop (ESU): | Chinook-Puget Sound, Threatened |
Chum-Pop (ESU): | Chum-Puget Sound/Strait of Georgia, Not Warranted |
City Areas: | Shelton |
Coho-Pop (ESU): | Coho-Puget Sound/Strait of Georgia, Species of Concern |
County: | Mason |
HUC12: | South Puget Sound (171100190900) |
HUC8: | Puget Sound (17110019) |
Lead Entity Area: | WRIA 14 |
Legislative District: | 35 |
Pink-Pop (ESU): | Pink-Odd Year, Not Warranted |
Puget Sound Action Areas: | South Puget Sound |
Salmon Recovery Regions: | Puget Sound |
Steelhead-Pop (ESU): | Steelhead-Puget Sound, Threatened |
Watershed Administrative Unit: | Mason |
WRIA: | Kennedy - Goldsborough |
APPLICATION | FINAL | ||||
RESTORATION METRICS | |||||
Miles of Stream and/or Shoreline Treated or Protected (C.0.b) | 0.22 | mi | |||
Estuarine / Nearshore Project | |||||
*Total Amount Of Estuarine / Nearshore Acres Treated (C.9.b) | 22.00 | acres | |||
Fill placement (C.9.h.1) | |||||
Acres of Estuary Treated with fill placement (C.9.h.2) | 22.00 | acres | |||
Shoreline armor removal or modification (C.9.k.1) | |||||
Acres of Shoreline Treated for armor modification/removal (C.9.k.3) | 0.30 | acres | |||
Miles of Shoreline Treated for armor modification/removal (C.9.k.2) | 0.17 | mi |