Coffee Creek Fish Passage Funding Package
#16-1675 #16-1675
 Oakland Bay / Hammersley Inlet Goldsborough Creek Coffee Creek Fish Passage Funding Package
Organization Kennedy-Goldsborough Basin (WRIA 14) Salmon Recovery Lead Entity
Sponsor Mason County Public Works
Status Dormant
Schedule Start Date: 1/1/2017 End Date: 12/31/2020
Category Category: Restoration
Project Photo
DESCRIPTION
South Puget Sound Salmon Enhancement Group and Mason County propose to restore fish passage at two select barrier culverts in the Coffee Creek drainage (Goldsborough Creek basin), Mason County, WRIA 14. The culvert on the southerly fork of Coffee Creek (under Deegan Road) is a total barrier; that on the West Fork of Coffee Creek (under Shelton Valley Road) is a partial barrier. Collectively, the barrier corrections will open up to 4.2 miles of rearing and spawning habitat for Coho Salmon, steelhead, and Cutthroat Trout.  This funding will complement the package submitted for funding to the Fish Passage Removal Board (FPRB) on behalf of the WRIA 14 Lead Entity. The two selected sites for barrier correction under this proposal are part of the larger seven barrier package forwarded to FPRB. Funds requested herein will be leveraged with the FPRB funding package to complete the funding need.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested08/11/2016Mason County Public WorksMatch$71,355.00
Requested08/11/2016Recreation and Conservation Office (RCO)Salmon State Projects$404,343.00
Allocated01/31/2018Mason County Public WorksMatch$71,355.00
Allocated01/31/2018Recreation and Conservation Office (RCO)Puget Sound Acq. & Restoration$404,343.00
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$1,861,000.00 $475,698.00 $475,698.00 $0.00 $475,698.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Puget Sound, Threatened
Chum-Pop (ESU):Chum-Puget Sound/Strait of Georgia, Not Warranted
Coho-Pop (ESU):Coho-Puget Sound/Strait of Georgia, Species of Concern
County:Mason
HUC12:Goldsborough Creek (171100190605)
HUC8:Puget Sound (17110019)
Lead Entity Area:WRIA 14
Legislative District:35
Pink-Pop (ESU):Pink-Odd Year, Not Warranted
Puget Sound Action Areas:South Puget Sound
Salmon Recovery Regions:Puget Sound
Sections:27
Steelhead-Pop (ESU):Steelhead-Puget Sound, South Puget Sound Tributaries, Threatened
Township:T20NR04W
Watershed Administrative Unit:Mason
WRIA:Kennedy - Goldsborough
View project on a larger map
  APPLICATION FINAL 
RESTORATION METRICS
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
0.01mi
Fish Passage Improvement    
*Miles Of Stream Made Accessible (SRFB) (C.2.b.1)
4.20mi
*Number of blockages / impediments / barriers impeding passage (C.2.b.4)
2.00
 Culvert installed or improved (C.2.f.1)    
Miles of stream made accessible by culvert installation/repair (C.2.f.3)
4.20mi
Number of culverts (C.2.f.2)
2.00