West Oakland Bay Restoration & Conservation
#15-1107 #15-1107
 Oakland Bay / Hammersley Inlet Nearshore West Oakland Bay Restoration & Conservation
Organization Kennedy-Goldsborough Basin (WRIA 14) Salmon Recovery Lead Entity
Sponsor South Puget Sound Salmon Enhancement Group (SPSSEG)
Status Completed
Schedule Start Date: 12/9/2015 End Date: 7/14/2020
Category Category: Acquisition & Restoration
Project Photo
DESCRIPTION
This project consists of 4 components of restoration, planning and conservation in the Goldsborough Creek estuary in Oakland Bay, South Puget Sound. The restoration component of the project consists of two related projects designed to rebuild lost salt marsh habitat. Component 1: Construction of up to 14-engineered logjams at the mouth of Goldsborough Creek designed to capture sediment to rebuild the creek mouth; Component 2: As phase one of a multi-phase project we will enhance the estuary and tidelands by importing bed material to create intertidal benches/shelves at appropriate elevations to allow for natural vegetation that will mesh with the creek mouth project; Component 3: A planning project will produce a final design for the removal of a bulkhead on Port of Shelton property on the north shore of the harbor. In a future phase we will reconfigure the shoreline to a more natural slope designed to fit with the Component 2 Shelton Harbor project; Component 4: This consists of a fee simple conservation acquisition of 14 acres of High Priority habitat on Eagle Point in Shelton Harbor. The property of interest includes 2 acres of freshwater wetland, 4 acres of tideland, 8 acres of riparian upland and 1600 feet of marine shoreline. All restoration will occur in areas rated as High Priority by the WRIA 14 technical committee and Enhance High Priority by PSNERP. This project is expected to benefit Chinook, coho and chum salmon as well as cutthroat and steelhead trout.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested08/10/2015South Puget Sound Salmon Enhancement Group (SPSSEG)Match$286,000.00
Requested08/10/2015Recreation and Conservation Office (RCO)Salmon State Projects$1,620,499.00
Allocated07/14/2020South Puget Sound Salmon Enhancement Group (SPSSEG)Match$354,125.00
Allocated07/14/2020Recreation and Conservation Office (RCO)Puget Sound Acq. & Restoration$1,897,374.00
Spent02/25/2020South Puget Sound Salmon Enhancement Group (SPSSEG)Match-$354,125.00
Spent02/25/2020Recreation and Conservation Office (RCO)Puget Sound Acq. & Restoration-$1,897,374.00
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
Not entered $1,906,499.00 $2,251,499.00 $2,251,499.00 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
SECONDARY SPONSOR
ALT PROJECT CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Puget Sound, Threatened
Chum-Pop (ESU):Chum-Puget Sound/Strait of Georgia, Not Warranted
City Areas:Shelton
Coho-Pop (ESU):Coho-Puget Sound/Strait of Georgia, Species of Concern
County:Mason
HUC12:Cranberry Creek-Frontal Oakland Bay (171100190606)
HUC12:South Puget Sound (171100190900)
HUC8:Puget Sound (17110019)
Lead Entity Area:WRIA 14
Legislative District:35
Pink-Pop (ESU):Pink-Odd Year, Not Warranted
Puget Sound Action Areas:South Puget Sound
Salmon Recovery Regions:Puget Sound
Sections:20
Sections:21
Steelhead-Pop (ESU):Steelhead-Puget Sound, South Puget Sound Tributaries, Threatened
Steelhead-Pop (ESU):Steelhead-Puget Sound, Threatened
Township:T20NR03W
Watershed Administrative Unit:Mason
WRIA:Kennedy - Goldsborough
View project on a larger map

Related Projects

  APPLICATION FINAL 
ACQUISTION METRICS
Real Property Acquisition    
Miles of Streambank and/or Shoreline Protected by Land or Easement Acquisition
0.30mi0.30mi
 Land    
Acres by Acreage Type (fee simple)
Lake
0.00
Riparian
8.00
Tidelands
4.00
Wetlands
2.00
Total
14.00
acres
Lake
0.00
Riparian
8.00
Tidelands
4.00
Wetlands
2.00
Total
14.00
acres
 
RESTORATION METRICS
Area Encompassed (acres) (B.0.b.1)
23.50acres10.50acres
Miles of Stream and/or Shoreline Affected (B.0.b.2)
0.00mi0.08mi
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
0.30mi0.87mi
Estuarine / Nearshore Project    
*Total Amount Of Estuarine / Nearshore Acres Treated (C.9.b)
23.50acres10.50acres
 Channel modification (C.9.c.1)    
Acres of Estuary Treated (C.9.c.3)
3.80acres10.50acres
Yards (linear measure) of Channel Modified/Created (C.9.c.2)
120.00yd
 Dike Or berm modification / removal (C.9.d.1)    
Acres of Habitat Made Available To Salmonids through dike or berm modification/removal (C.9.d.3)
2.10acres0.00acres
Miles Of Dikes Modified/Removed (C.9.d.2)
0.25mi0.00mi
 Fill placement (C.9.h.1)    
Acres of Estuary Treated with fill placement (C.9.h.2)
13.40acres6.50acres
 Shoreline armor removal or modification (C.9.k.1)    
Acres of Shoreline Treated for armor modification/removal (C.9.k.3)
0.20acres
Miles of Shoreline Treated for armor modification/removal (C.9.k.2)
0.21mi
ADDITIONAL INFORMATION