Big Cove Restoration
#07-1822 #07-1822
Organization Kennedy-Goldsborough Basin (WRIA 14) Salmon Recovery Lead Entity
Sponsor South Puget Sound Salmon Enhancement Group (SPSSEG)
Status Completed
Schedule Start Date: 12/13/2007 End Date: 1/19/2011
Category Category: Restoration
Project Photo
DESCRIPTION
This project removed shoreline armoring, a defunct tidal dam, and silty material from a small estuary in Big Cove, Totten Inlet. The desired project repaired one-half an acre of nearshore / freshwater fringe habitat and improved access to a small freshwater stream. The historical conditions of the site would be conducive for coastal cutthroat, coho, and chum salmon. This project reestablished a natural tidal connectivity to the upstream available habitat. Tons of rip rap and an abandoned culvert were removed from the shoreline. Portions of the embankment were graded to create a stable slope. The existing conditions offer an unique opportunity for restoration at a small watershed scale. An earthen dam has recently failed and has re-exposed this site. The up stream habitat has been impounded by 10 feet of water for nearly 40 years. After the earthen dam failed boulders toppled and created a barrier tidal outlet condition. Upstream of the dam there is a 2 acre flat area that has become infested with reed canary grass. Historically the site was “fringe” forested habitat and was productive. Part of the SPSSEG action plan will be to plant native 5 gallon potted plants back into the disturbed area and add LWD. The larger plants will be used to out-compete the reed canary grass and over time to re-establish a functional forested watershed.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested09/21/2007South Puget Sound Salmon Enhancement Group (SPSSEG)Match$11,168.00
Requested09/21/2007Recreation and Conservation Office (RCO)Puget Sound Acq. & Restoration$63,228.00
Allocated06/08/2010South Puget Sound Salmon Enhancement Group (SPSSEG)Match$16,492.00
Allocated06/08/2010Recreation and Conservation Office (RCO)Puget Sound Acq. & Restoration$78,108.00
Spent01/19/2011South Puget Sound Salmon Enhancement Group (SPSSEG)Match-$16,492.00
Spent01/19/2011Recreation and Conservation Office (RCO)Puget Sound Acq. & Restoration-$78,108.00
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$96,208.00 $74,396.00 $94,600.00 $94,600.00 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
ALT PROJECT CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Puget Sound, Threatened
Chum-Pop (ESU):Chum-Puget Sound/Strait of Georgia, Not Warranted
Coho-Pop (ESU):Coho-Puget Sound/Strait of Georgia, Species of Concern
County:Mason
HUC12:South Puget Sound (171100190900)
HUC8:Puget Sound (17110019)
Lead Entity Area:WRIA 14
Legislative District:35
Pink-Pop (ESU):Pink-Odd Year, Not Warranted
Puget Sound Action Areas:South Puget Sound
Salmon Recovery Regions:Puget Sound
Steelhead-Pop (ESU):Steelhead-Puget Sound, Threatened
Watershed Administrative Unit:Mason
WRIA:Kennedy - Goldsborough
View project on a larger map
  APPLICATION FINAL 
RESTORATION METRICS
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
0.00mi0.20mi
Estuarine / Nearshore Project    
*Total Amount Of Estuarine / Nearshore Acres Treated (C.9.b)
2.00acres0.50acres
 Channel modification (C.9.c.1)    
Acres of Estuary Treated (C.9.c.3)
0.50acres
Yards (linear measure) of Channel Modified/Created (C.9.c.2)
0.00yd
 Creation of new estuarine area (C.9.q.1)    
Acres of Estuary Created (C.9.q.2)
1.00acres0.00acres
 Culvert modification / removal (C.9.f.1)    
Acres Opened To Fish Passage through culvert modification/removal (C.9.f.3)
0.50acres
Miles of stream made accessible by removal or modification of culvert
Number of Culverts Modified/Removed To Allow Fish Passage (C.9.f.2)
1.00
 Dike Or berm modification / removal (C.9.d.1)    
Acres of Habitat Made Available To Salmonids through dike or berm modification/removal (C.9.d.3)
0.50acres
Miles Of Dikes Modified/Removed (C.9.d.2)
 Estuarine plant removal / control (C.9.j.1)    
Acres of Estuary Treated for plant removal/control (C.9.j.3)
2.00acres0.20acres
 Regrading of slope (C.9.i.1)    
Acres of Estuary Treated through slope regrading (C.9.i.2)
0.50acres
 Shoreline armor removal or modification (C.9.k.1)    
Acres of Shoreline Treated for armor modification/removal (C.9.k.3)
0.10acres
Miles of Shoreline Treated for armor modification/removal (C.9.k.2)
0.05mi
Instream Habitat Project    
Total Miles Of Instream Habitat Treated (C.4.b)
0.10mi
 Channel structure placement (C.4.d.1)    
Acres Of Streambed Treated for channel structure placement (C.4.d.4)
0.10acres
Miles of Stream Treated for channel structure placement (C.4.d.3)
0.10mi
Number of structures placed in channel (C.4.d.7)
3.00
Pools Created through channel structure placement (C.4.d.5)
3.00
Yards Of Average Stream-Width At Mid-Point Of Worksite (C.4.d.6)
Riparian Habitat Project    
*Total Riparian Acres Treated (C.5.b.2)
0.10acres
*Total Riparian Miles Streambank Treated (C.5.b.1)
0.20mi
 Planting (C.5.c.1)    
Acres Planted in riparian (C.5.c.3)
0.10acres
ADDITIONAL INFORMATION