Moon Island Design and Restoration
#18-1201 #18-1201
Organization Chehalis Basin Lead Entity
Sponsor City of Hoquiam
Status Completed
Schedule Start Date: 1/19/2018 End Date: 6/21/2021
Category Category: Planning & Restoration
DESCRIPTION
Phase 1 of the Moon Island Project: Conduct a feasibility analysis of the removal of the riprap and rubble from the shoreline and the potential to relocate Moon Island Road away from the shoreline approximately 20 to 30 feet. The shoreline is armored with riprap and is filled with chunks of asphalt and concrete rubble that splash into the mudflats. These characteristics of the shoreline do not provide a natural setting suitable for quality habitat or roadway protection.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested05/02/2018Recreation and Conservation Office (RCO)WA Coast Rst Resiliency Proj$400,000.00
Allocated06/25/2018Recreation and Conservation Office (RCO)WA Coast Rst Resiliency Proj$400,000.00
Spent06/21/2021City of HoquiamMatch-$0.00
Spent06/21/2021Recreation and Conservation Office (RCO)WA Coast Rst Resiliency Proj-$400,000.00
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$150,000.00 $400,000.00 $400,000.00 $400,000.00 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Washington Coast, Not Warranted
Chum-Pop (ESU):Chum-Pacific Coast, Not Warranted
City Areas:Hoquiam
Coho-Pop (ESU):Coho-Southwest Washington, Not Determined
County:Grays Harbor
HUC12:Fry Creek-Frontal Grays Harbor (171001050204)
HUC12:Grays Harbor (171001050400)
HUC8:Grays Harbor (17100105)
Lead Entity Area:Chehalis Basin
Legislative District:24
Salmon Recovery Regions:Washington Coast
Sections:10
Steelhead-Pop (ESU):Steelhead-Washington Coast, Not Warranted
Township:T17NR10W
Watershed Administrative Unit:WF-MF Hoquiam
WRIA:Lower Chehalis
View project on a larger map
  APPLICATION FINAL 
PLANNING/RESTORATION METRICS
Area Encompassed (acres) (B.0.b.1)
3.50acres3.50acres
Miles of Stream and/or Shoreline Affected (B.0.b.2)
0.45mi0.45mi
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
0.45mi0.45mi
Estuarine / Nearshore Project    
*Total Amount Of Estuarine / Nearshore Acres Treated (C.9.b)
3.50acres3.50acres
 Shoreline armor removal or modification (C.9.k.1)    
Acres of Shoreline Treated for armor modification/removal (C.9.k.3)
3.50acres3.50acres
Miles of Shoreline Treated for armor modification/removal (C.9.k.2)
0.50mi0.50mi
ADDITIONAL INFORMATION