The Quinault Indian Nation completed construction of the Alder Creek Side Channel Pilot Project in 2008. The project consisted of building 12 engineered logjams (ELJs), an island-edge tree reinforced log lattice (TRL), and stabilizing an existing natural logjam with log pilings. The purpose of the project was to initiate restoration of the upper Quinault River and to demonstrate the restoration approach identified in the Salmon Habitat Restoration Plan-Upper Quinault River (QIN 2008). The plan (and pilot project) is a result of recommendations made in the Geomorphic Assessment of the Quinault River, Washington (USBOR 2005). The plan is a comprehensive restoration strategy based on nearly 30 years of riverine-forest-salmon habitat scientific research. The ELJs and TRL were designed by ENTRIX, Inc. ENTRIX also provided construction oversight and certification for the completed structures. The structures were built by DO Construction with labor provided by local contractors. Logs for the project were provided by Olympic National Park and Olympic National Forest. Quinault Valley Forestry transported and stored the logs used in the project. The project was completed in compliance with all state and federal regulatory permits and consultations.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested09/17/2007Quinault Indian NationMatch$66,450.00
Requested09/17/2007Recreation and Conservation Office (RCO)Salmon State Projects$376,550.00
Allocated05/21/2008Quinault Indian NationMatch$67,600.00
Allocated05/21/2008Recreation and Conservation Office (RCO)Salmon State Projects$383,000.00
Spent11/06/2009Quinault Indian NationMatch-$67,600.00
Spent11/06/2009Recreation and Conservation Office (RCO)Salmon State Projects-$383,000.00
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$450,600.00 $443,000.00 $450,600.00 $450,600.00 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Washington Coast, Not Warranted
Chum-Pop (ESU):Chum-Pacific Coast, Not Warranted
Coho-Pop (ESU):Coho-Olympic Peninsula, Not Warranted
County:Jefferson
HUC12:Finley Creek-Quinault River (171001020407)
HUC8:Queets-Quinault (17100102)
Lead Entity Area:Quinault Indian Nation
Legislative District:24
Salmon Recovery Regions:Washington Coast
Sections:36
Sockeye-Pop (ESU):Sockeye-Quinault Lake, Not Warranted
Steelhead-Pop (ESU):Steelhead-Olympic Peninsula, Not Warranted
Township:T24NR09W
Watershed Administrative Unit:Quinault Lake
WRIA:Queets - Quinault
View project on a larger map
  APPLICATION FINAL 
RESTORATION METRICS
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
0.50mi0.50mi
Instream Habitat Project    
Total Miles Of Instream Habitat Treated (C.4.b)
2.20mi2.20mi
 Channel structure placement (C.4.d.1)    
Acres Of Streambed Treated for channel structure placement (C.4.d.4)
40.00acres
Miles of Stream Treated for channel structure placement (C.4.d.3)
2.20mi
Number of structures placed in channel (C.4.d.7)
10.00
Pools Created through channel structure placement (C.4.d.5)
12.00
Yards Of Average Stream-Width At Mid-Point Of Worksite (C.4.d.6)
400.00yd
 Streambank stabilization (C.4.e.1)    
Miles of Streambank Stabilized (C.4.e.3)