Organization | Quinault Indian Nation Lead Entity |
Sponsor | Quinault Indian Nation |
Status | Completed |
Schedule | Start Date: 3/1/2008 End Date: 11/6/2009 |
Category | Category: Restoration |
Type | Date | Funding Org | Funding Program | Match | Amount |
---|---|---|---|---|---|
Requested | 09/17/2007 | Quinault Indian Nation | Match | $66,450.00 | |
Requested | 09/17/2007 | Recreation and Conservation Office (RCO) | Salmon State Projects | $376,550.00 | |
Allocated | 05/21/2008 | Quinault Indian Nation | Match | $67,600.00 | |
Allocated | 05/21/2008 | Recreation and Conservation Office (RCO) | Salmon State Projects | $383,000.00 | |
Spent | 11/06/2009 | Quinault Indian Nation | Match | -$67,600.00 | |
Spent | 11/06/2009 | Recreation and Conservation Office (RCO) | Salmon State Projects | -$383,000.00 |
Grant Project Agreement Totals | Proposed | Requested | Allocated | Spent | Balance |
$450,600.00 | $443,000.00 | $450,600.00 | $450,600.00 | $0.00 |
Type | Date | Funding Org | Funding Program | Match | Amount |
---|
Other Funding Totals | Proposed | Requested | Allocated | Spent | Balance |
Grand Totals | Proposed | Requested | Allocated | Spent | Balance |
Chinook-Pop (ESU): | Chinook-Washington Coast, Not Warranted |
Chum-Pop (ESU): | Chum-Pacific Coast, Not Warranted |
Coho-Pop (ESU): | Coho-Olympic Peninsula, Not Warranted |
County: | Jefferson |
HUC12: | Finley Creek-Quinault River (171001020407) |
HUC8: | Queets-Quinault (17100102) |
Lead Entity Area: | Quinault Indian Nation |
Legislative District: | 24 |
Salmon Recovery Regions: | Washington Coast |
Sections: | 36 |
Sockeye-Pop (ESU): | Sockeye-Quinault Lake, Not Warranted |
Steelhead-Pop (ESU): | Steelhead-Olympic Peninsula, Not Warranted |
Township: | T24NR09W |
Watershed Administrative Unit: | Quinault Lake |
WRIA: | Queets - Quinault |
APPLICATION | FINAL | ||||
RESTORATION METRICS | |||||
Miles of Stream and/or Shoreline Treated or Protected (C.0.b) | 0.50 | mi | 0.50 | mi | |
Instream Habitat Project | |||||
Total Miles Of Instream Habitat Treated (C.4.b) | 2.20 | mi | 2.20 | mi | |
Channel structure placement (C.4.d.1) | |||||
Acres Of Streambed Treated for channel structure placement (C.4.d.4) | 40.00 | acres | |||
Miles of Stream Treated for channel structure placement (C.4.d.3) | 2.20 | mi | |||
Number of structures placed in channel (C.4.d.7) | 10.00 | ||||
Pools Created through channel structure placement (C.4.d.5) | 12.00 | ||||
Yards Of Average Stream-Width At Mid-Point Of Worksite (C.4.d.6) | 400.00 | yd | |||
Streambank stabilization (C.4.e.1) | |||||
Miles of Streambank Stabilized (C.4.e.3) | 0.50 | mi | 0.50 | mi |