Wisen Creek Barrier Corrections x3 Project, Ph 2
#21-1470 #21-1470
 Quillayute River Basin Management Unit Sol Duc River Wisen Creek Barrier Corrections x3 Project, Ph 2
Organization North Pacific Coast Lead Entity
Sponsor Trout Unlimited - WA Coast
Status Dormant
Schedule Start Date: 7/1/2023 End Date: 6/30/2025
Category Category: Restoration
DESCRIPTION
Correction of three culvert barriers on Wisen Creek and Wisen Branch Creek in the Sol Duc Watershed.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested01/13/2022Recreation and Conservation Office (RCO)BA Fish Barrier Removal Board$544,400.00
Requested01/13/2022Trout Unlimited - WA CoastMatch$688,800.00
Allocated07/01/2023Recreation and Conservation Office (RCO)BA Fish Barrier Removal Board$544,400.00
Allocated07/01/2023Trout Unlimited - WA CoastMatch$688,800.00
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$350,000.00 $1,233,200.00 $1,233,200.00 $0.00 $1,233,200.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
ALT PROJECT CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Washington Coast, Not Warranted
Chum-Pop (ESU):Chum-Pacific Coast, Not Warranted
Coho-Pop (ESU):Coho-Olympic Peninsula, Not Warranted
County:Clallam
HUC12:Beaver Creek-Sol Duc River (171001010605)
HUC8:Hoh-Quillayute (17100101)
Lead Entity Area:North Pacific Coast
Legislative District:24
Salmon Recovery Regions:Washington Coast
Sections:30
Steelhead-Pop (ESU):Steelhead-Olympic Peninsula, Not Warranted
Township:T30NR11W
Watershed Administrative Unit:Sol Duc Valley
WRIA:Soleduc
View project on a larger map
  APPLICATION FINAL 
RESTORATION METRICS
Fish Passage Improvement    
*Miles Of Stream Made Accessible (SRFB) (C.2.b.1)
0.00mi
*Number of blockages / impediments / barriers impeding passage (C.2.b.4)
3.00
Miles Of Stream Made Accessible (FBRB)
1.20mi
 Culvert installed or improved (C.2.f.1)    
Miles of stream made accessible by culvert installation/repair (C.2.f.3)
1.80mi
Number of culverts (C.2.f.2)
3.00