Braden Creek Culvert Replacement
#W20-10-81068 #W20-10-81068
 Hoh River Basin Management Unit Braden Creek Braden Creek Culvert Replacement
Organization North Pacific Coast Lead Entity
Sponsor Hoh River Trust
Status Completed
Schedule Start Date: 4/1/2010 End Date: 10/15/2010
Category Category: Restoration
DESCRIPTION
Two culverts were replaced, road repair and upgrade. Commercial thinning at 20% to prescription on 63 acres.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested10/11/2024Hoh River Trust$8,000.00
Allocated10/11/2024Hoh River Trust$8,000.00
Spent10/17/2024Hoh River Trust-$8,000.00
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$8,000.00 $8,000.00 $8,000.00 $8,000.00 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Washington Coast, Not Warranted
Chum-Pop (ESU):Chum-Pacific Coast, Not Warranted
Coho-Pop (ESU):Coho-Olympic Peninsula, Not Warranted
County:Jefferson
HUC12:Nolan Creek-Hoh River (171001010707)
HUC8:Hoh-Quillayute (17100101)
Lead Entity Area:North Pacific Coast
Legislative District:24
Salmon Recovery Regions:Washington Coast
Sections:27
Steelhead-Pop (ESU):Steelhead-Olympic Peninsula, Not Warranted
Township:T26NR13W
Watershed Administrative Unit:Lower Hoh River
WRIA:Soleduc
View project on a larger map
ADDITIONAL INFORMATION