Sands Creek Drainage Culvert Replacement
#12-1408 #12-1408
 Quillayute River Basin Management Unit Dickey River Sands Creek Drainage Culvert Replacement
Organization North Pacific Coast Lead Entity
Sponsor Pacific Coast Salmon Coalition
Status Completed
Schedule Start Date: 12/6/2012 End Date: 4/12/2016
Category Category: Restoration
Project Photo
DESCRIPTION
For this restoration project the Pacific Coast Salmon Coalition replaced the undersized, perched culvert with a bridge in an effort to return the stream to a natural state and allow access to the 1.25 miles of spawning and rearing habitat above the blockage. The project site is located at mile post 14.5 on Rayonier Inc.'s 9000 mainline road. Sands Creek in the Dickey Watershed in Clallam County, WA. This project opened additional access to habitat in a system that is important spawning and rearing habitat to Coho, Chinook, winter steelhead and cutthroat trout. During construction a blue clay seam was discovered in the streambank. This soil type is extremely unstable causing work to be shutdown. The sponsor and landowner were forced to go back to design to address this safety issue. The new design and design solution to ensure the new bridge would be safe caused project costs to exceed the original budget.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested08/24/2012Recreation and Conservation Office (RCO)Salmon State Projects$116,737.00
Requested08/24/2012Pacific Coast Salmon CoalitionMatch$290,119.00
Allocated04/12/2016Recreation and Conservation Office (RCO)Salmon Federal Projects$166,587.00
Allocated04/12/2016Pacific Coast Salmon CoalitionMatch$339,969.00
Spent01/28/2015Recreation and Conservation Office (RCO)Salmon State Projects-$0.00
Spent04/12/2016Recreation and Conservation Office (RCO)Salmon Federal Projects-$166,587.00
Spent04/12/2016Pacific Coast Salmon CoalitionMatch-$339,969.00
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$506,556.00 $406,856.00 $506,556.00 $506,556.00 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Proposed Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Washington Coast, Not Warranted
Chum-Pop (ESU):Chum-Pacific Coast, Not Warranted
Coho-Pop (ESU):Coho-Olympic Peninsula, Not Warranted
County:Clallam
HUC12:West Fork Dickey River (171001010301)
HUC8:Hoh-Quillayute (17100101)
Lead Entity Area:North Pacific Coast
Legislative District:24
Salmon Recovery Regions:Washington Coast
Sections:10
Steelhead-Pop (ESU):Steelhead-Olympic Peninsula, Not Warranted
Township:T30NR14W
Watershed Administrative Unit:WF Dickey
WRIA:Soleduc
View project on a larger map
  APPLICATION FINAL 
RESTORATION METRICS
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
0.01mi0.01mi
Fish Passage Improvement    
*Miles Of Stream Made Accessible (SRFB) (C.2.b.1)
1.50mi1.50mi
*Number of blockages / impediments / barriers impeding passage (C.2.b.4)
1.00
Square Miles Of streambed made accessible (C.2.b.2)
0.00sq mi0.10sq mi
 Bridge installed or improved (C.2.g.1)    
Miles of stream made accessible by bridge installation/repair (C.2.g.3)
1.50mi1.50mi
Number of bridges (C.2.g.2)
1.001.00