Organization | North Pacific Coast Lead Entity |
Sponsor | Pacific Coast Salmon Coalition |
Status | Completed |
Schedule | Start Date: 9/26/2008 End Date: 6/23/2011 |
Category | Category: Restoration |
Type | Date | Funding Org | Funding Program | Match | Amount |
---|---|---|---|---|---|
Requested | 04/21/2009 | Pacific Coast Salmon Coalition | Match | $5,000.00 | |
Requested | 04/21/2009 | Recreation and Conservation Office (RCO) | FFFPP Grants | $95,528.00 | |
Allocated | 06/06/2011 | Pacific Coast Salmon Coalition | Match | $4,370.18 | |
Allocated | 06/06/2011 | Recreation and Conservation Office (RCO) | FFFPP Grants | $70,577.82 | |
Spent | 06/06/2011 | Pacific Coast Salmon Coalition | Match | -$4,370.18 | |
Spent | 06/06/2011 | Recreation and Conservation Office (RCO) | FFFPP Grants | -$70,577.82 |
Grant Project Agreement Totals | Proposed | Requested | Allocated | Spent | Balance |
$100,528.00 | $100,528.00 | $74,948.00 | $74,948.00 | $0.00 |
Type | Date | Funding Org | Funding Program | Match | Amount |
---|
Other Funding Totals | Proposed | Requested | Allocated | Spent | Balance |
Grand Totals | Proposed | Requested | Allocated | Spent | Balance |
Chinook-Pop (ESU): | Chinook-Washington Coast, Not Warranted |
Chum-Pop (ESU): | Chum-Pacific Coast, Not Warranted |
Coho-Pop (ESU): | Coho-Olympic Peninsula, Not Warranted |
County: | Jefferson |
HUC12: | Nolan Creek-Hoh River (171001010707) |
HUC8: | Hoh-Quillayute (17100101) |
Lead Entity Area: | North Pacific Coast |
Legislative District: | 24 |
Salmon Recovery Regions: | Washington Coast |
Sections: | 28 |
Steelhead-Pop (ESU): | Steelhead-Olympic Peninsula, Not Warranted |
Township: | T26NR13W |
Watershed Administrative Unit: | Lower Hoh River |
WRIA: | Soleduc |
APPLICATION | FINAL | ||||
RESTORATION METRICS | |||||
Miles of Stream and/or Shoreline Treated or Protected (C.0.b) | 0.00 | mi | 0.20 | mi | |
Fish Passage Improvement | |||||
*Miles Of Stream Made Accessible (SRFB) (C.2.b.1) | 2.11 | mi | 2.11 | mi | |
*Number of blockages / impediments / barriers impeding passage (C.2.b.4) | 1.00 | ||||
Miles Of Stream Made Accessible (FFFPP) | |||||
Square Miles Of streambed made accessible (C.2.b.2) | 0.00 | sq mi | |||
Bridge installed or improved (C.2.g.1) | |||||
Miles of stream made accessible by bridge installation/repair (C.2.g.3) | 2.11 | mi | |||
Number of bridges (C.2.g.2) | 1.00 | ||||
Culvert installed or improved (C.2.f.1) | |||||
Miles of stream made accessible by culvert installation/repair (C.2.f.3) | 2.11 | mi | 2.11 | mi | |
Number of culverts (C.2.f.2) | 1.00 | ||||
Fish passage blockages removed or altered (C.2.c.1) | |||||
Number of Blockages/Impediments/Barriers Removed/Altered (C.2.c.2) | 1.00 | 1.00 | |||
Road-crossing removal (C.2.i.1) | |||||
Miles of stream made accessible by road crossing removal (C.2.i.3) | 0.00 | mi | 0.00 | mi | |
Number of road-crossings (C.2.i.2) | 0.00 |