Coal Creek Culvert Replacement
#11-1462 #11-1462
Organization North Pacific Coast Lead Entity
Sponsor Pacific Coast Salmon Coalition
Status Completed
Schedule Start Date: 12/8/2011 End Date: 10/31/2014
Category Category: Restoration
Project Photo
DESCRIPTION
This Road Maintenance and Abandonment Plan (RMAP) restoration project to address fish passage is located in Clallam County on an unnamed tributary of Coal Creek, which is a tributary to the Dickey River. The Dickey River and its tributaries provide abundant low-gradient habitat for spawning and rearing coho salmon, and steelhead and cutthroat trout. The Dickey drainage is known as one of the top coho smolt producers (measured by square kilometer of drainage) in Washington State. The Dickey confluences with the Quillayute River in the Quillayute Esturary. The sponsor removed an undersized, deteriorating, and perched, 96" culvert and replacing it with a 60' bridge. The new structure allows fish passage under all flow conditions. The new bridge was installed at the 8.2 mile on the 5000 line, a heavily used logging road. The average width of the creek upstream of the project is 14’. The undersized culvert created conditions that resulted in a 20” outfall drop that plunged directly onto large rip rap, placed to protect the road, creating an obstacle to salmonid migrating upstream to access the habitat above the blocking culvert. Wood and gravel were also added to the stream to enhance the habitat, the entire site was planted with native vegetation, and an interpretive sign was installed.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested08/26/2011Pacific Coast Salmon CoalitionMatch$91,200.00
Requested08/26/2011Recreation and Conservation Office (RCO)Salmon State Projects$169,300.00
Allocated10/31/2014Pacific Coast Salmon CoalitionMatch$89,281.08
Allocated10/31/2014Recreation and Conservation Office (RCO)Salmon Federal Projects$165,735.01
Spent01/08/2014Recreation and Conservation Office (RCO)Salmon State Projects-$0.00
Spent10/31/2014Pacific Coast Salmon CoalitionMatch-$89,281.08
Spent10/31/2014Recreation and Conservation Office (RCO)Salmon Federal Projects-$165,735.01
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$260,500.00 $260,500.00 $255,016.09 $255,016.09 $0.00
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Washington Coast, Not Warranted
Chum-Pop (ESU):Chum-Pacific Coast, Not Warranted
Coho-Pop (ESU):Coho-Olympic Peninsula, Not Warranted
County:Clallam
HUC12:Coal Creek-Dickey River (171001010303)
HUC8:Hoh-Quillayute (17100101)
Lead Entity Area:North Pacific Coast
Legislative District:24
Salmon Recovery Regions:Washington Coast
Sections:26
Steelhead-Pop (ESU):Steelhead-Olympic Peninsula, Not Warranted
Township:T29NR15W
Watershed Administrative Unit:Lower Dickey
WRIA:Soleduc
View project on a larger map
  APPLICATION FINAL 
RESTORATION METRICS
Miles of Stream and/or Shoreline Treated or Protected (C.0.b)
2.90mi2.90mi
Fish Passage Improvement    
*Miles Of Stream Made Accessible (SRFB) (C.2.b.1)
2.90mi2.90mi
*Number of blockages / impediments / barriers impeding passage (C.2.b.4)
1.00
Square Miles Of streambed made accessible (C.2.b.2)
0.00sq mi0.00sq mi
 Bridge installed or improved (C.2.g.1)    
Miles of stream made accessible by bridge installation/repair (C.2.g.3)
2.90mi2.90mi
Number of bridges (C.2.g.2)
1.001.00